ROCK CREEK - CRESTA PROJECT

FERC Project No. 1962

 

 

 

Rock Creek - Cresta Relicensing

Settlement Agreement

 

 

 

 

 

Electronic Distribution Copy

December 6, 2000

 

 

Note:  As of December 6, 2000, the text of the electronic file of this document (written in Word 7 for Windows 95) matches the text of the Rock Creek - Cresta Relicensing Settlement Agreement executed September 18, 2000 and filed with FERC by letter dated September 29, 2000.  However, an individual’s computer equipment and settings may result in changes to the format of the electronic file or of a printed copy made from the electronic file compared to the signed Settlement filed with FERC.  Additionally, because the electronic file is easily changed, there can be no assurance that the electronic file or a printed copy made from the electronic file has not been modified subsequent to December 6, 2000.  The Rock Creek - Cresta Relicensing Settlement Agreement filed with FERC by letter dated September 29, 2000 and recorded in FERC’s record management system should be used as the definitive version of the signed Settlement.

 

 

 

File: RCCSettle Elect.doc

 


Rock Creek - Cresta Project

FERC Project No. 1962

 

Rock Creek -Cresta Relicensing Settlement Agreement

 

Table of Contents

Page

 

1.     Introduction

 

 

1.1   Parties

1

1.2   Recitals

1

1.3   Effective Date of Settlement

2

1.4   Term of Settlement

2

1.5   Definitions

2

 

2.     Purpose of Settlement

 

 

2.1   Purpose

5

2.2   Resolved Subjects

5

2.3  Unresolved Subjects

6

2.4  Relationship to 1991 Fish and Wildlife Agreement

6

2.5   No Precedent for Other Proceedings

6

2.6   Compliance with Legal Responsibilities

6

2.7   Reservation of Claims, Rights, and Responsibilities

7

2.8   Term of New Project License

7

 

3.     Use of Settlement in New Project License and Section 4(e) Conditions

 

 

3.1   Protection, Mitigation, and Enhancement Measures Recommended to be Included in New Project License

7

3.2  Protection, Mitigation, and Enhancement Measures Recommended to be Included in    Section 4(e) Conditions

8

3.3  Relationship of Settlement to Section 7 Consultation

8

3.4   Measures Agreed to But Not to be Included in New Project License or Section 4(e) Conditions

8

 

4.  Implementation of Settlement

 

 

4.1   Support of Settlement

8

4.2  Support for Issuance of New Project License

8

4.3  New Project License, Final 4(e) Conditions, or Other Mandatory Conditions Inconsistent with this Settlement

9


 

 

page

 

4.4  Appeal of New Project License, Final 4(e) License Conditions, or Other Mandatory    Conditions Inconsistent with this Settlement

10

4.5  Cooperation Among Parties

11

4.6  Implementation Schedule

13

4.7  Reopener or Amendment of New Project License

13

4.8  Amendment of Settlement

14

4.9  Dispute Resolution

14

4.10 Withdrawal from Settlement

15

4.11 Termination of Settlement

16

 

5.     General Provisions

 

 

5.1   Non-Severable Terms of Settlement

17

5.2   No Third Party Beneficiaries

17

5.3   Successors and Assigns

17

5.4   Failure to Perform Due to Force Majeure

17

5.5   Governing Law

18

5.6   Elected Officials Not to Benefit

18

5.7   No Partnership

18

5.8   Reference to Regulations

18

5.9   Notice

18

5.10 Paragraph Titles for Convenience Only

18

 

6.     Execution of Settlement

 

 

6.1  Signatory Authority

18

6.2   Disclosure of Other Agreements

19

6.3  Signing in Counterparts

19

 

Appendix A. Protection, Mitigation, and Enhancement Measures Recommended to be Included in New Project License, Section 4(e) Conditions, and Other Mandatory License Conditions

 

 

Section I.       Water Temperature Management

A-1

Section II.      River Flow Management

A-6

Section III      Habitat Improvements

A-27

Section IV.     River Sediment Management

A-28

Section V.      Recreation Flow Management

A-29

Section VI.     River Recreation Facilities

A-32

Section VII.    Public Recreation Monitoring

A-33

Section VIII.   Ecological Resources Committee

A-33

 

Appendix B. Measures Agreed to Among the Parties But Not to be Included in New Project License, Section 4(e) Conditions, or Other Mandatory License Conditions

 

 

Section I.       Objectives

B-1

Section II.      Ecological Resources Committee

B-5

Section III      Habitat Mitigation

B-8

Section IV.     Block Loading

B-11

Section V.      Monitoring Plan

B-11

 

 

Appendix C.  Authorized Representatives of Parties

C-1

 

 

 

 


 

 

Rock Creek - Cresta Project

FERC Project No. 1962

 

 

 

 

Relicensing Settlement Agreement

 

 

 

 

 

 

 

1.            Introduction

 

1.1      Parties. This SETTLEMENT AGREEMENT ("Settlement") is made and entered into pursuant to Federal Energy Regulatory Commission (“FERC”) Rule 602, 18 CFR § 385.602, by and among Pacific Gas and Electric Company (“Licensee”), the United States Department of Agriculture Forest Service (“FS”), the United States Department of the Interior Fish and Wildlife Service (“FWS”), the California Department of Fish and Game (“CDFG”), California State Water Resources Control Board (‘SWRCB”), Natural Heritage Institute (“NHI”), American Whitewater (“AW”), Friends of the River (“FOR”), Plumas County (“PC”), California Outdoors (“CO”), California Trout (“CT”), Chico Paddleheads (“CP”), and Shasta Paddlers (“SP”) each referred to individually as a “Party” and collectively as “Parties.”  These thirteen Parties may also be referred to as the “Original Parties.”

 

The Parties to this Settlement agree as follows:

 

1.2      Recitals

 

          1.2.1    On September 28, 1979, Licensee filed with the Federal Energy Regulatory Commission (“FERC”) an application for a new license (“New Project License”) for the Rock Creek - Cresta Project, FERC Project No. 1962 (“Project”) located on the North Fork Feather River (“NFFR”) in Plumas and Butte counties, California.

 

          1.2.2    On October 9, 1991 Licensee and CDFG entered into a Fish and Wildlife Agreement (“1991 Fish and Wildlife Agreement”) to establish minimum streamflows and other resource management measures for the protection, mitigation, and enhancement (“PM&E”) of fish and wildlife resources affected by the Project. This Agreement updates and supersedes the 1991 Fish and Wildlife Agreement.

 

          1.2.3    On March 15, 1996 FS issued revised preliminary conditions for the Project pursuant to 18 CFR §4.34 b(1) and in furtherance of its mandatory conditioning authority under Section 4(e) (“Preliminary 4(e) Conditions”) of the Federal Power Act (“FPA”).  Various Parties and others subsequently submitted comments and appeals to FERC and FS regarding the Preliminary 4(e) Conditions.

 

          1.2.4    On November 1, 1996 FERC issued a Draft Environmental Assessment for the Project  (“DEA”) pursuant to the National Environmental Policy Act (“NEPA”).  Various Parties and others subsequently submitted comments to FERC regarding the DEA.

 

          1.2.5    In July 1998, Licensee, FS, FWS, CDFG, SWRCB, AW, FOR, PC, NHI, CT, California Sportfishing Protection Alliance, SP, and CP met and agreed to engage in discussions to resolve issues related to flow in the Rock Creek and Cresta reaches of the NFFR.  Since those initial discussions, Licensee has provided several progress updates to the FERC and requested that additional time be allowed to continue the process.  Over time the group became known as the Rock Creek - Cresta Relicensing Collaborative (“Collaborative”) and subcommittees were formed to discuss technical issues on fisheries and whitewater recreation.  Meetings of the Collaborative were publicly noticed by FERC.

 

          1.2.6    This Settlement is an end product of the Collaborative’s work.

 

1.3      Effective Date of Settlement.  This Settlement becomes effective as of September 18, 2000 (“Effective Date”).

 

1.4      Term of Settlement.  The term of this Settlement shall commence on the Effective Date and shall continue (unless terminated as otherwise provided herein) for the term of the New Project License (subject to FERC's reserved authority under the New Project License to require modifications), plus the term(s) of any annual license(s) which may be issued after the foregoing New Project License has expired, or until the effective date of any FERC order approving surrender of all or part of the Project under the FPA.

 

1.5            Definitions.  

 

i.                   AF:  acre-foot of water

ii.                 ADR:  Alternative Dispute Resolution - see Paragraph 4.9.1.

iii.               Basin Plan:  The Water Quality Control Plan for the Central Valley Region, the Sacramento and San Joaquin River Basins


iv.                Beneficial Uses:  Beneficial Uses include municipal and domestic water supply, hydropower generation, water contact recreation, canoeing and rafting, non-contact water recreation, cold freshwater habitat, cold freshwater spawning habitat, and wildlife habitat, as designated in the Basin Plan, or any revision thereto.

v.                  Block Loading:  Operational mode of a powerhouse in which the generation capacity (and resulting cfs release) is held at or near a constant level for an extended period of time.

vi.                Cap Flows:  Maximum level to which the Minimum River Flow level may be adjusted as provided in Appendix A, Table A.

vii.              CD:  Critically Dry water year type as defined in Appendix A, Section II.

viii.            cfs:  cubic feet per second

ix.                Collaborative:  See Paragraph 1.2.5.

x.                  Controlled Spill:  Release of water from a Project reservoir at times when the release could have otherwise been controlled (not spilled) by increasing the flow through the generating units or controlling inflows by controlling releases from upstream reservoirs.

xi.                Cresta Reach:  That portion of the NFFR between Cresta Dam and the Cresta Powerhouse.

xii.              DEA:  Draft Environmental Assessment - see Paragraph 1.2.4.

xiii.            Disputing Party; Disputing Parties:  See Paragraph 4.9.1.

xiv.             Dry:  Dry water year type as defined in Appendix A, Section II.

xv.               Effective Date:  See Paragraph 1.3.

xvi.             ESA:  Federal Endangered Species Act - see Paragraph 2.6.1.

xvii.           ERC:  Ecological Resources Committee as established in Appendix A, Section VIII and as fully described in Appendix B, Section II.

xviii.         FPA:  Federal Power Act - see Paragraph 1.2.3.

xix.             Good Faith:  Honesty of purpose, free from intention to defraud, faithful to one’s duty or obligation.

xx.               Heat Storm: A multi-day sequence of extreme temperatures across California or the western-U.S. that results in near-record electricity use and voluntary power use reductions or involuntary, rotating power outages. 

xxi.             Inconsistent with this Settlement: See Paragraph 4.3.1.

xxii.           Minimum River Flows:  Required minimum flows in the Rock Creek and Cresta reaches as provided in Section II of Appendix A.

xxiii.         NA:  not applicable

xxiv.          NFFR:  North Fork Feather River

xxv.            NEPA:  National Environmental Protection Act - see Paragraph 1.2.4.

xxvi.          New Project License:  See Paragraph 1.2.1.

xxvii.        1991 Fish and Wildlife Agreement.  See Paragraph 1.2.2

xxviii.      Normal: Normal water year type as defined in Appendix A, Section II.

xxix.          Notice: See Paragraph 5.9.

xxx.            Prattville Intake Modifications:  Physical improvements in the vicinity of the Prattville Intake to attract cold water to the intake.

xxxi.          Party; Parties:  See Paragraph 1.1.

xxxii.        PM&E:  protection, mitigation or enhancement measure.

xxxiii.      Project:  See Paragraph 1.2.1.

xxxiv.       Pulse Flows:  Short term elevated levels of release from Projects dams in amounts and durations specified in Appendix A, Table A.

xxxv.         Ramping Rate:  The rate of change in a flow release or spill from a dam expressed as an increase or decrease in discharge (in cfs) over a period of time.  See Appendix A, Section II.5.

xxxvi.       Reasonable Control Measures:  Measures to control water temperatures as specified in Section I of Appendix A.

xxxvii.     Resolved Subjects:  See Paragraph 2.2.

xxxviii.    Rock Creek Reach:  That portion of the NFFR between Rock Creek Dam and Rock Creek Powerhouse.

xxxix.       Section 4(e) Conditions: Any revision of FS’ proposed license conditions under FPA Section 4(e) subsequent to the Preliminary 4(e) Conditions issued on March 15, 1996.

xl.                Submerged Curtain/Skimmer Wall:  A design concept for a Prattville Intake Modification that consists of a flexible membrane blocking warm water strata and up to 1250 feet long placed upstream of the Prattville Intake to allow the intake to attract colder water

xli.              Uncontrolled Spill:  Release of water from a Project reservoir at times when flow into the reservoir, excluding releases from upstream reservoirs that can be controlled, exceeds to sum of the instream flow release requirement plus the current flow capacity of the generating units.

xlii.            Water Year Type:  See Appendix A, Section II.

xliii.          Wet:  Wet water year type as defined in Appendix A, Section II.

 

 


2.   Purpose of Settlement

 

2.1      Purpose. The purpose of this Settlement is to resolve among the Parties all streamflow issues for ecological purposes and river-based recreational use and other Resolved Subjects in support of FS issuing its Final 4(e) Conditions and FERC issuing a New Project License.  For this purpose, the Parties agree that this Settlement constitutes an entire agreement that provides an appropriate balancing of hydroelectric power generation with the Resolved Subjects.

 

2.2      Resolved Subjects.  Except as provided in Paragraph 2.3, the Parties agree that this Settlement fairly, reasonably, and appropriately resolves streamflows and other subjects listed in Table 1 (“Resolved Subjects”) in support of FS issuing Final 4(e) Conditions and FERC issuing a New Project License.   

 

Table 1

 

Subjects Resolved by this Settlement

 

(a)    Streamflows for PM&E of fish, wildlife, and other aquatic biota in Project-affected stream reaches

(b)    Streamflows for PM&E of riparian habitat in Project-affected stream reaches

(c)    Streamflows for stream channel maintenance in Project-affected stream reaches

(d)    Streamflows for whitewater boating and other river-based recreation on the Rock Creek and Cresta reaches

(e)    Water quality associated with Project operations and facilities, including water temperatures

(f)    Streamflow fluctuations from Project operations, including Ramping Rates

(g)    Streamflow gaging for compliance monitoring

(h)    Stream ecology monitoring

(i)    Whitewater boating use monitoring

(j)    Streamflow information for use by the public

(k)    Access facilities for whitewater boating on the Rock Creek and Cresta reaches

(m)    Adjustment of PM&E measures stated in Appendix A and B through adaptive management over the term of the license

(n)    Facility modifications to implement the PM&E measures stated in Appendix A

(o)    Administration of Settlement Agreement

(p)  Term of New Project License

(q)  River sediment management

 


2.3      Unresolved Subjects.  This Settlement leaves unresolved specific subjects related to the Resolved Subjects.  These unresolved subjects are listed in Table 2.  This Settlement also does not resolve subjects not specifically listed in Table 1 and Table 2. 

 

Table 2

 

Disputed Subjects Not Resolved by this Settlement

 

(a)  Regulatory approvals needed for relicensing of the Project.

(b)  Reasonable water temperature control measures for protection of water quality of the NFFR that may be sought or required in the relicensing proceedings for the North Fork Feather River Project (No. 2105) and Poe Project (No. 2107); or in any proceeding to amend the New Project License to provide for coordinated operations of this Project, the North Fork Feather River Project, and the Poe Project.

 

2.4      Relationship to 1991 Fish and Wildlife Agreement. This Settlement supersedes the 1991 Fish and Wildlife Agreement, provided CDFG and Licensee are Parties.  If CDFG or Licensee is not a Party or withdraws from this Settlement, then the superseded terms of the 1991 Fish and Wildlife Agreement shall be revived and again become in full force and effect between Licensee and CDFG to the extent permissible under applicable state and federal law.

 

2.5      No Precedent for Other Proceedings.  This Settlement is made upon the express understanding that it constitutes a negotiated resolution of Resolved Subjects.  No Party shall be deemed to have approved, admitted, accepted, or otherwise consented to any operation, management, valuation, or other principle underlying or supposed to underlie any of the Resolved Subjects, except as expressly provided herein.  Nothing in this Settlement is intended or shall be construed as a precedent with regard to any other proceeding or hydroelectric project, except as expressly provided in Appendix A, Section I.

 

2.6      Compliance with Legal Responsibilities.  Nothing in this Settlement is intended to or shall be construed to affect or limit the authority of any Party to fulfill its statutory, regulatory, or contractual responsibilities under applicable law.  However, by entering into this Settlement the Parties with such responsibilities represent that they believe their responsibilities relative to Resolved Subjects have been, are, or can be met for the purpose stated in Paragraph 2.1, consistent with and by the terms of this Settlement.

 

          2.6.1    ESA and FPA Section 18 Responsibilities Not Affected.  Nothing in this Settlement is intended to or shall be construed to restrict or affect the continuing responsibilities of FERC or any Party under the Endangered Species Act (“ESA”), including the implementing regulation at 50 C.F.R. § 402.16.   Further, notwithstanding any other provision in this Settlement, this Settlement is not intended to and shall not be construed to address, affect, or apply to the Secretary of the United States Department of the Interior’s independent authority under FPA Section 18 to prescribe fishways, or Licensee’s right to dispute such authority.

 

2.6.2   CWA Responsibilities Not Affected.  Nothing in this Settlement is intended to or shall be construed to limit or otherwise affect the authority or responsibilities of Licensee, SWRCB, or any other Party under the Clean Water Act, Porter-Cologne Water Quality Control Act, or implementing regulations, in connection with: (a) the relicensing proceedings for the North Fork Feather River Project (No. 2105) and Poe Project (No. 2107); or (b) any proceeding to amend the New Project License to protect Beneficial Uses through coordinated operations of the Project, the North Fork Feather River Project and Poe Project.  In particular, this Settlement shall not affect the SWRCB’s authority to impose additional or more stringent requirements for Project Nos. 2105 and 2107 as part of the relicensing proceedings for those projects.  In any proceeding where the SWRCB has legal authority to require compliance with water quality standards or other appropriate requirements, and in light of its 1987 waiver of the water quality certification of the New Project License for this Project, this Settlement shall not be construed as a representation that the measures incorporated into this Settlement are adequate to ensure compliance with such standards and requirements.

 

2.7      Reservation of Claims, Rights, and Responsibilities.  Each Party reserves all claims, rights, and responsibilities, which it may otherwise have with respect to any subjects not listed as Resolved Subjects.  Nothing in this Settlement is intended or shall be construed to affect or restrict any Party's participation in or comments about compliance with the New Project License, future relicensing of the Project subsequent to the current relicensing, or any other project licensed to Licensee.

 

2.8      Term of New Project License.  The Parties agree that the term of the New Project License shall be for a nominal period of 30 years and do not object if the FERC may choose to extend the term as needed to make the Project No. 1962 license expiration coincident with the expiration of new licenses anticipated on Project No. 2105 and No. 2107. 

 

 

3.         Use of Settlement in New Project License and Section 4(e) Conditions 

 

3.1      Protection, Mitigation, and Enhancement Measures Recommended to be Included in New Project License.  Subject to Paragraphs 3.2 and 3.3, the Parties respectfully request that FERC accept and incorporate, without material modification, as license articles all of the PM&E measures stated in Appendix A of this Settlement. Subject to the same limitation, the Parties further request that FERC not include in the New Project License additional articles on Resolved Subjects except as may be necessary to enable FERC to ascertain and monitor Licensee’s compliance with the conditions of the New Project License and its rules and regulations under the FPA.

               

3.2      Protection, Mitigation, and Enhancement Measures Recommended to be Included in Section 4(e) Conditions.  The Parties respectfully request that FS accept and incorporate, without material modification, as Section 4(e) Conditions all relevant PM&E measures stated in Appendix A of this Settlement. The Parties further request that FS not include in its Section 4(e) Conditions additional conditions on Resolved Subjects.  FS agrees to propose as Section 4(e) Conditions on Resolved Subjects the PM&E measures stated in Appendix A of this Settlement which it determines are within its jurisdiction to prescribe as Section 4(e) Conditions, except to the extent that any changes result from its analysis under NEPA, National Forest Management Act, and any other applicable law or regulation.  This paragraph shall not be read to predetermine or limit the outcome or lawful discretion of FS in issuing Section 4(e) Conditions or in adopting Section 4(e) Conditions inconsistent with those recommended herein.

 

3.3     Relationship of  Settlement to Section 7 Consultation.  The Parties acknowledge that if FERC submits the PM&E measures stated in Appendix A as part of the proposed action for consultation under Section 7 of the ESA, FWS may in its lawful discretion identify PM&E measures different from or additional to those set forth in Appendix A and Appendix B to minimize the effects of take of listed species.

 

            3.4       Measures Agreed to But Not  to be Included in the New Project License or Section 4(e) Conditions.  Measures agreed to among the Parties which are not to be incorporated in the New Project License or FS Section 4(e) Conditions are stated in Appendix B.  

 

 

4.            Implementation of Settlement

 

4.1      Support of Settlement. The Parties shall be bound by this Settlement for the term stated in Paragraph 1.4, provided the New Project License is consistent with the terms of this Settlement, and specifically the PM&E measures stated in Appendix A hereto.

 

4.2       Support for Issuance of New Project License.  To the extent permitted by applicable law, the Parties shall support or advocate through appropriate written communications to FERC and FS, this Settlement and the PM&E measures stated in Appendix A hereto.  For Resolved Subjects and subject to Paragraph 3.3, the Parties agree not to propose, support, or communicate to FERC or FS any comments, recommended PM&E measures, or license conditions other than ones consistent with this Settlement.  Subject to Paragraph 3.3,  prior to the issuance of the New Project License, and at the request of Licensee, the Parties shall timely support this Settlement in written communications to any other administrative agency with advisory or mandatory conditioning authority over issuance of the New Project License, provided this sentence shall not apply to the agency exercising the authority.

 

4.3      New Project License, Final 4(e) Conditions, or Other Mandatory Conditions Inconsistent with this Settlement

 

          4.3.1    New Project License.  If the New Project License issued by FERC contains any material modification of the PM&E measures stated in Appendix A or Appendix B, incorporates fewer than all of the PM&E measures stated in Appendix A, or includes additional measures related to Resolved Subjects (“inconsistent with this Settlement”), this Settlement shall be deemed modified to conform to the New Project License, unless a Party provides Notice that it disputes the inconsistency within 30 days after the date of the license order, and that Party initiates the Alternative Dispute Resolution (“ADR”) procedures stated in Paragraph 4.9.1 - Paragraph 4.9.3.  The disputing Party(s) may, in addition, initiate the rehearing procedure described in Paragraph 4.4.1.  If the New Project License does not contain all of the PM&E measures stated in Appendix A because FERC expressly determines that it does not have jurisdiction to adopt or enforce the omitted PM&E measures, the Parties agree that they shall be bound by the entire Settlement, including those recommended PM&E measures omitted by FERC, provided the New Project License contains those PM&E measures stated in Appendix A over which FERC determines it does have jurisdiction and the New Project License is otherwise consistent with this Settlement.

 

          4.3.2    Final 4(e) Conditions.  If any Final 4(e) Condition is inconsistent with this Settlement, this Settlement shall be deemed modified to conform to the Final 4(e) Conditions, unless a Party provides Notice that it disputes the inconsistency during the 45-day appeal period under 36 CFR § 215.13, and that Party initiates the ADR procedures stated in Paragraph 4.9.1 - Paragraph 4.9.3.  The disputing Party(s) may, in addition, initiate the appeal procedure described in Paragraph 4.4.2.  If the Final 4(e) Conditions do not contain all of the PM&E measures stated in Appendix A because FS expressly determines that it does not have jurisdiction to adopt or enforce the omitted PM&E measures, the Parties shall be bound by the entire Settlement, including those recommended PM&E measures omitted by FS, provided the Final 4(e) Conditions contain those PM&E measures stated in Appendix A over which FS determines it does have jurisdiction and the Final 4(e) Conditions are otherwise consistent with this Settlement.

 

          4.3.3    Other Mandatory License Conditions.  If an agency other than FS files with FERC any mandatory license condition that is inconsistent with this Settlement, this Settlement shall be deemed modified to conform to such condition, unless a Party provides Notice that it disputes the inconsistency within 30 days after the date of filing of such condition, and that Party initiates the ADR procedures stated in Paragraph 4.9.1 - Paragraph 4.9.3.  The disputing Party(s) may, in addition, initiate any appeal procedure applicable to the agency that issued such condition.  If such mandatory license conditions do not contain all of the PM&E measures stated in Appendix A because the issuing agency expressly determines that it does not have jurisdiction to adopt or enforce the omitted PM&E measures, the Parties agree that they shall be bound by the entire Settlement, including those recommended PM&E measures omitted by the issuing agency, provided the mandatory license conditions contain those PM&E measures stated in Appendix A over which issuing agency determines it does have jurisdiction, and the mandatory license conditions are otherwise consistent with this Settlement.

 

            4.4      Appeal of New Project License, Final 4(e) Condition, or other Mandatory License Conditions Inconsistent with this Settlement.

 

          4.4.1    Appeal to FERC.  Any Party may petition FERC for rehearing or seek judicial review of any New Project License article, or omission of PM&E measures stated in Appendix A, that is inconsistent with this Settlement.  The ADR requirements stated in Paragraph 4.9.1 - Paragraph 4.9.3 do not preclude any Party from timely filing for and pursuing rehearing under 18 C.F.R. § 385.713(b), or judicial review, of the inconsistent license article or any other license article that relates to subjects not listed as a Resolved Subject.   However, the Parties shall follow the ADR procedures stated in Paragraph 4.9.1 - Paragraph 4.9.3 to the extent reasonably practicable while such appeal of an inconsistency is pursued.  If any Party or non-Party files for administrative rehearing or judicial review of any New Project License article that is inconsistent with this Settlement, Licensee’s duties under this Settlement related to that article are suspended to the extent necessary to enable Licensee to comply with the license.  If a Party has filed for rehearing or judicial review of any New Project License article that is inconsistent with this Settlement and the Parties subsequently agree to modify this Settlement to conform to the inconsistent article, the filing Party(s) shall withdraw the appeal, or recommend such withdrawal, as appropriate. Except as provided in Paragraph 4.3.1 for omissions based on jurisdiction, if  any New Project License article is inconsistent with this Settlement after a final and non-appealable administrative or judicial decision on the appeal, this Settlement shall be deemed modified to conform to the final decision unless a Party provides Notice that it disputes the inconsistency within 45 days after the date of the final decision and initiates the ADR procedures stated in Paragraph 4.9.1 - Paragraph 4.9.3.  Except as necessary to fulfill a statutory or regulatory responsibility or policy, the Parties have a continuing duty to support this Settlement, or as appropriate, recommend such support, during an administrative rehearing or judicial review.

 

                  4.4.2      Appeal to FS.  A Party may seek administrative rehearing or judicial review of any Final 4(e) Condition, or omission of PM&E measures stated in Appendix A, that is inconsistent with this Settlement.  The ADR requirements of Paragraph 4.9.1 - Paragraph 4.9.3 do not preclude any Party from timely filing and pursuing an appeal under 36 CFR § 215.13, or judicial review, of any Final 4(e) Condition that is inconsistent with this Settlement, or any other Final 4(e) Condition that relates to subjects not listed as a Resolved Subject.  However, the Parties shall follow ADR procedures stated in Paragraph 4.9.1 - Paragraph 4.9.3 to the extent reasonably practicable while any such appeal of an inconsistency is pursued.  If a Party has filed for administrative rehearing or judicial review of any Final 4(e) Condition that is inconsistent with this Settlement and the Parties subsequently agree to modify this Settlement to conform to the inconsistent condition, the filing Party(s) shall withdraw the appeal, or recommend such withdrawal, as appropriate. Except as provided in Paragraph 4.3.2 for omissions based on jurisdiction if any Final 4(e) Condition is inconsistent with this Settlement after the final and non-appealable decision on appeal, this Settlement shall be deemed modified to conform to the final decision, unless a Party provides Notice that it disputes the inconsistency within 45 days after the date of the final decision, and that Party initiates the ADR procedures stated in Paragraph 4.9.1 - Paragraph 4.9.3.  Except as necessary to fulfill a statutory or regulatory responsibility or policy, all Parties have a continuing duty to support this Settlement, or as appropriate, recommend such support, during an administrative rehearing or judicial review.

 

          4.4.3                        Appeal to other Agency with Mandatory Conditioning Authority. Any Party may seek administrative rehearing or judicial review of any mandatory license condition that, as filed with FERC by an agency other than FS, is inconsistent with this Settlement.  The ADR requirements stated in Paragraph 4.9.1 - Paragraph 4.9.3 do not preclude any Party from timely filing and pursuing such appeal of a mandatory license condition that is inconsistent with this Settlement, or any other mandatory license condition that relates to subjects not listed as a Resolved Subject.  However, the Parties shall follow ADR procedures stated in Paragraph 4.9.1 - Paragraph 4.9.3 to the extent reasonably practicable while any such appeal of an inconsistency is pursued.  If a Party has filed for administrative rehearing or judicial review of any mandatory license condition that is inconsistent with this Settlement, and the Parties subsequently agree to modify this Settlement to conform to the inconsistent condition, the filing Party(s) shall withdraw the appeal, or recommend such withdrawal, as appropriate.  If any mandatory license condition is still inconsistent with this Settlement after a final and non-appealable administrative or judicial decision on the appeal, this Settlement shall be deemed modified to conform to the final decision, unless a Party provides Notice that it disputes the inconsistency within 45 days after the date of the final decision, and that Party also initiates the ADR procedures stated in Paragraph 4.9.1 - Paragraph 4.9.3.  Except as necessary to fulfill a statutory or regulatory responsibility or policy, all Parties have a continuing duty to support this Settlement, or as appropriate, recommend such support, during such administrative rehearing or judicial review.

 

4.5      Cooperation Among Parties. The Parties shall cooperate in the performance of this Settlement and compliance with related license articles.  Among other things, the Parties shall cooperate in implementing the PM&E measures, conducting studies, performing monitoring, and conducting all other activities within their statutory or regulatory authorities related to the measures stated in Appendices A & B of this Settlement, as may be modified in the New Project License.  Further, subject to Paragraph 2.6, inclusive of 2.6.1 and 2.6.2, and upon Licensee’s request, the Parties shall provide written communications of support in any administrative approval that may be required for implementation of this Settlement or related articles of the New Project License, provided this sentence shall not apply to the agency exercising the authority. 

 

          4.5.1      Responsibility for Costs.  Licensee shall pay for the cost of actions required of Licensee by this Settlement or the New Project License.  Licensee shall have no obligation to reimburse or otherwise pay any other Party for its assistance, participation, or cooperation in any activities pursuant to this Settlement or the New Project License unless expressly agreed to by Licensee or as required by law.

 

          4.5.2      Licensee Solely Responsible for Operations of Project.  By entering into this Settlement, none of the Parties, except for Licensee, have accepted any legal liability or responsibility for the operation of the Project.

 

          4.5.3      Availability of Funds.  Implementation of this Settlement for a Party that is a federal agency is subject to the requirements of the Anti-Deficiency Act, 31 United States Code, Section 1341, and the availability of appropriated funds.  Nothing in this Settlement is intended or shall be construed to require the obligation, appropriation, or expenditure of any money from the U.S. Treasury.  The Parties acknowledge that the Parties that are federal agencies shall not be required under this Settlement to expend any federal agency’s appropriated funds unless and until an authorized official of each such agency affirmatively acts to commit such expenditures as evidenced in writing.  Implementation of this Settlement by Parties that are state agencies is subject to the availability of appropriated funds.  Nothing in this Settlement is intended or shall be construed to require the obligation, appropriation, or expenditure of any money from the Treasury of the State of California.  The Parties acknowledge that the Parties that are state agencies shall not be required under this Settlement to expend any appropriated funds unless and until an authorized official of each such agency affirmatively acts to commit such expenditures as evidenced in writing.

 

          4.5.4    FS Participation in Settlement.  FS is not included in the definition of the words “Party” or “Parties” as used in Paragraphs 3.1, 3.2, 4.1, 4.2, 4.3.2, 4.4.1, 4.4.2, 4.5, and 4.7.1 of this Settlement.  Additionally, FS’ obligations under and participation in this Settlement are fulfilled upon issuance of a New Project License containing Final 4(e) Conditions that are no longer subject to administrative appeal or judicial review.  Notwithstanding any provision to the contrary, nothing in this Settlement is intended or shall be construed to create FS authority over a subject that is not within its existing authority.

 

          4.5.5  Escalation of Costs.  Unless otherwise indicated, costs specified as a year 2000 cost basis shall be escalated (starting in January 2001) based on the U. S. Gross Domestic Product - Implicit Price Deflator (GDP-IPD).  Costs not specified as a year 2000 cost basis are constant dollars not subject to escalation.

 

4.6      Implementation Schedule.  Implementation of the PM&E measures stated in Appendix A shall begin after issuance of the New Project License and consistent with the schedule specified in Appendix A (as may be modified by the New Project License). Implementation of the measures stated in Appendix B shall begin consistent with the schedule specified in Appendix B.  Within six months after issuance of the New Project License, Licensee shall prepare and provide to all Parties Licensee’s planned schedule for implementing the PM&E measures recommended in this Settlement and incorporated in the New Project License.  The schedule shall specify dates for initiation, progress reporting, monitoring and completion, as appropriate, for each such PM&E measure and shall include milestones for major activities.

 

            4.7            Reopener or Amendment of New Project License

 

          4.7.1      Reopener.  Except as required to fulfill statutory or regulatory responsibilities or as provided in Paragraph 4.7.2, a Party to this Settlement may seek to modify, or otherwise reopen during the term of this Settlement the PM&E measures from this Settlement included in the New Project License, only if and when significant new information not known or understood as of the date of issuance of the New Project License reasonably demonstrates that such proposed modification or other cause of reopener is in furtherance of the public interest under the FPA or other applicable law.  In such an event, that Party shall provide Licensee at least 90-day Notice to consider the new information and that Party’s position.   A Party shall not be required to comply with this 90-day Notice provision if it believes an emergency situation exists, or if required to meet its responsibilities under applicable law.  Notwithstanding the provisions of this paragraph, any Party may seek to reopen the New Project License to implement future changes in applicable law, or to protect Beneficial Uses through coordinated operations of this Project, North Fork Feather River Project (No. 2105), and Poe Project (No. 2107), in connection with the relicensing proceedings for the latter two projects.

 

          4.7.2      Amendment.   Nothing in this Settlement is intended or shall be construed to affect or limit the right of Licensee to seek amendments of the New Project License, provided that Licensee may seek a Project license amendment which would adversely affect this Settlement only if Licensee, relying on significant new information not known or understood as of the date of issuance of the New Project License, can reasonably demonstrate in the amendment proceeding that the amendment is in furtherance of the public interest under the FPA or other applicable law.  Prior to filing a proposed license amendment which relates to a Resolved Subject or would otherwise  affect this Settlement, Licensee shall provide the Parties at least 90-day Notice of its intention to do so, and promptly following the giving of such Notice, shall consult with Parties responding within 30 days of such Notice regarding the need for and the purpose of the amendment, provided Licensee shall not be required to comply with this 90-day Notice provision if it believes an emergency situation exists or if required to meet its responsibilities under applicable law or an order of an agency with jurisdiction over Licensee.  In such an emergency situation, Licensee shall give Notice to the ERC and FS within 5 days of the event.  In any application for a Project license amendment that relates to a Resolved Subject or would otherwise affect this Settlement, Licensee shall provide with its application documentation of its consultation with the responsive Parties, summarize the positions and recommendation of the responsive Parties and provide its response to those positions and recommendations.  Licensee shall not oppose an intervention request by any Party that satisfies FERC’s procedural requirements in a proceeding for a Project license amendment that any Party has concluded would adversely affect this Settlement.  A Project license amendment that, as approved by FERC, would adversely affect this Settlement is subject to Paragraph 4.3.1.  Further, a Project license amendment that, as approved by FERC, would adversely affect this Settlement may be considered by a Party as significant new information, allowing that Party to invoke the reopener provision in Paragraph 4.7.1.

 

4.8      Amendment of Settlement.  This Settlement may be amended at any time through the term of the New Project License plus the term(s) of any annual license(s) which may be issued after the foregoing New Project License has expired, after Notice, with the unanimous agreement of all Parties still in existence and responsive within 30 days of such Notice.  Any amendment of this Settlement shall be in writing and executed by the responding Parties.

 

            4.9      Dispute Resolution

 

          4.9.1      General.  Except to the extent that FERC, FS, or other agency with jurisdiction over a Resolved Subject has a procedure that precludes implementation of Paragraph 4.9.1 - Paragraph 4.9.3, and to the extent specified for the ERC in Appendix B, all disputes among the Parties regarding any Party’s performance or compliance with this Settlement, including resolution of any disputes related to any New Project License article, Final 4(e) Condition, or mandatory license condition filed with FERC by an agency other than the FS, that is inconsistent with this Settlement, shall be the subject of a non-binding alternative dispute resolution (“ADR”) procedure among the disputing Parties, as stated in this Paragraph 4.9.1 - Paragraph 4.9.3.  Each Party participating in a dispute (“disputing Party,” or collectively, “disputing Parties”) shall cooperate in Good Faith to promptly schedule, attend and participate in the ADR.  The disputing Parties agree to devote such time, resources and attention to the ADR as is needed to attempt to resolve the dispute at the earliest time possible.  Each disputing Party shall implement promptly all final agreements reached, consistent with its applicable statutory and regulatory responsibilities.  Nothing in Paragraph 4.9.1 - Paragraph 4.9.3 is intended or shall be construed to affect or limit the authority of FERC, FS, or other agency with jurisdiction over a Resolved Subject, to resolve a dispute brought before it in accord with its own procedure and applicable law.

 

                        4.9.2            ADR Procedures.  A Party claiming a dispute shall give Notice of the dispute within 30 days of the Party’s actual knowledge of the act, event, or omission that gives rise to the dispute, unless this Settlement provides otherwise.  If the dispute includes a claim that any New Project License article, Section 4(e) Condition, or mandatory license condition filed with FERC by an agency other than FS, is inconsistent with this Settlement, and the claim arises prior to rehearing or appeal, the Notice shall be made within the time periods specified in Paragraphs 4.3.1, 4.3.2, or 4.3.3, respectively.  If the dispute includes a claim that any New Project License article, Section 4(e) Condition, or mandatory license condition filed with FERC by an agency other than FS, is inconsistent with this Settlement, and the claim arises during or after rehearing or appeal, the Notice shall be made within the time periods specified in Paragraphs 4.4.1, 4.4.2, and 4.4.3, respectively.  At a minimum and in any dispute subject to these ADR procedures, the disputing Parties shall hold two informal meetings within 30 days after Notice, to attempt to resolve the disputed issue(s).  Any disputing Party may request that a FERC employee facilitate these informal meetings to assist in resolving the dispute.  If the informal meetings fail to resolve the dispute, the disputing Parties shall attempt to resolve the dispute using a neutral mediator jointly selected within 15 days after Notice by a disputing Party that the informal meetings did not resolve the dispute.  The disputing Parties shall select a mediator from the sources described in 18 CFR §385.604(c)(3). Absent an agreement for equitable allocation of costs of the mediator, the Parties shall select a FERC employee as mediator.  The mediator shall mediate the dispute during the next 60 days after their selection.  Any of these time periods may be reasonably extended or shortened by agreement of the disputing Parties, or as necessary to conform to the procedure of an agency or court with jurisdiction over the dispute.  Unless otherwise agreed among the disputing Parties, each disputing Party shall bear its costs for its own participation in the ADR procedures.

 

          4.9.3      Enforcement of Settlement After Dispute Resolution. Any Party may seek in a court of competent jurisdiction specific performance of this Settlement by any other Party, after compliance with the ADR procedures stated in Paragraph 4.9.1 -Paragraph 4.9.3.  No Party shall be liable in damages for any breach of this Settlement, any performance or failure to perform a mandatory or discretionary obligation imposed by this Settlement, or any other cause of action arising from this Settlement.  The time used to comply with the ADR procedures shall be excluded from computing any applicable statute of limitations, except where applicable law precludes such exclusion when computing time.  Nothing in Paragraph 4.9.1 - Paragraph 4.9.3 is intended or shall be construed to affect or limit the jurisdiction of any agency or court as established under applicable law.

 

4.10      Withdrawal From Settlement.

 

          4.10.1      Withdrawal of a Party from Settlement.  A Party may withdraw from this Settlement only in the following circumstances: (a) a disputing Party claiming a material breach or violation of this Settlement may withdraw once the Party has complied with the ADR procedures stated in Paragraph 4.9.1 - Paragraph 4.9.3 to attempt to resolve the dispute; or (b) a Party objecting to a final and non-appealable order issuing a New Project License that is inconsistent with this Settlement may withdraw once the Party has complied with the ADR procedures stated in Paragraph 4.9.1 - Paragraph 4.9.3 to attempt to resolve the objection.  In addition, Licensee may withdraw as provided in Paragraph 4.10.2.  In addition, when required to fulfill statutory or regulatory responsibility, a Party that is an agency may suspend participation or, if necessary, withdraw from this Settlement, without first using the ADR procedures stated in Paragraph 4.9.1 - Paragraph 4.9.3.  Finally, a Party may withdraw as provided in Paragraph 5.3.

     

          4.10.2      Withdrawal of Licensee from Settlement.  In addition to the provisions of Paragraph 4.10.1, Licensee may withdraw from this Settlement without first complying with the ADR procedures stated in Paragraph 4.9.1 - Paragraph 4.9.3 if a participant in the Collaborative does not execute, or in the case of the FWS, initial this Settlement by the Effective Date, or a Party withdraws from this Settlement, and Licensee reasonably determines at its sole discretion that the failure to execute or the withdrawal (a) may adversely affect the likelihood of FS issuing Final 4(e) Conditions consistent with this Settlement; (b) may adversely affect FERC’s issuance of a New Project License consistent with this Settlement; or (c) substantially diminishes the value of this Settlement to Licensee.  Licensee shall exercise the right to withdraw from this Settlement as provided in this paragraph within 30 days of Licensee’s knowledge of the event creating the right to withdraw.

          

           4.10.3  Method of Withdrawal.  A Party may exercise its right to withdraw from this Settlement by giving Notice.  Withdrawal is effective 10 calendar days after Notice. A Party that is an agency may suspend participation in this Settlement as provided in Paragraph 4.10.1 by giving Notice.

 

          4.10.4      Continuity After Withdrawal. The withdrawal of a Party, other than Licensee, does not terminate this Settlement for the remaining Parties.  If a Party withdraws from this Settlement, the withdrawing Party shall not be bound by any term contained in this Settlement.  Additionally, except for Licensee, the withdrawing Party shall be deemed to have resigned from the ERC upon the effective date of the withdrawal and shall not be eligible for membership in the ERC for a period of 5 years. The withdrawing Party shall continue to be bound by the Collaborative protocols, to the extent permitted by applicable law.

 

4.11      Termination of Settlement.  This Settlement shall terminate as to all Parties and have no further force or effect upon expiration of the New Project License and any annual licenses issued after expiration thereof or upon withdrawal from this Settlement of Licensee.  If this Settlement is terminated, this Settlement and all documents related to its development, execution, and submittal to FERC shall be deemed confidential and shall not be discoverable or admissible in any forum or proceeding for any purpose to the fullest extent allowed by applicable law, including 18 C.F.R. § 385.606.  This provision does not apply to the results of resource studies or other technical information developed for use by the Collaborative.

 

 

5.            General Provisions

 

5.1      Non-Severable Terms of Settlement.  The terms of this Settlement are not severable one from the other.  This Settlement is made on the understanding that each term is in consideration and support of every other term, and each term is a necessary part of the entire Settlement.

 

5.2      No Third Party Beneficiaries.  Without limiting the applicability of rights granted to the public pursuant to applicable law, this Settlement shall not create any right or interest in the public, or any member thereof, as a third party beneficiary hereof, and shall not authorize any non-Party to maintain a suit at law or equity pursuant to this Settlement.   The duties, obligations and responsibilities of the Parties with respect to third parties shall remain as imposed under applicable law.

 

5.3      Successors and Assigns. This Settlement shall apply to, and be binding on, the Parties and their successors and assigns.  Upon completion of a succession or assignment, the initial Party shall no longer be a Party to this Settlement.  No change in ownership of the Project or transfer of the existing or New Project License by Licensee shall in any way modify or otherwise affect any other Party’s interests, rights, responsibilities or obligations under this Settlement.  Unless prohibited by applicable law, Licensee shall provide in any transaction for a change in ownership of the Project or transfer of the existing or New Project License, that such new owner shall be bound by, and shall assume the rights and obligations of this Settlement upon completion of the change of ownership and approval by FERC of the license transfer.  In the event applicable law prohibits the new owner from assuming the rights and obligations of this Settlement, any Party may withdraw from this Settlement.  A transferring or assigning Party shall provide Notice to the other Parties at least 30 days prior to completing such transfer or assignment.

 

5.4      Failure to Perform Due to Force Majeure.  No Party shall be liable to any other Party for breach of this Settlement as a result of a failure to perform or for delay in performance of any provision of this Settlement due to any cause reasonably beyond its control.  This may include, but is not limited to, natural events, labor or civil disruption, or breakdown or failure of Project works.  The Party whose performance is affected by a force majeure shall make notify the other Parties in writing within seven (7) days after becoming aware of any event that such affected Party contends constitutes a force majeure.  Such notice will: identify the event causing the delay or anticipated delay; estimate the anticipated length of delay; state the measures taken or to be taken to minimize the delay; and estimate the timetable for implementation of the measures.  The affected Party shall make all reasonable efforts to promptly resume performance of this Settlement, and, when able to resume performance of its obligations and give the other Parties written notice to that effect.

 

5.5      Governing Law.  The New Project License and any other terms of this Settlement over which a federal agency has jurisdiction shall be governed, construed, and enforced in accordance with the statutory and regulatory authorities of such agency.  This Settlement shall otherwise be governed and construed under the laws of the State of California.  By executing this Settlement, no federal agency is consenting to the jurisdiction of a state court unless such jurisdiction otherwise exists.  All activities undertaken pursuant to this Settlement shall be in compliance with all applicable law.

 

5.6      Elected Officials Not to Benefit.  No member of or delegate to Congress shall be entitled to any share or part of this Settlement or to any benefit that may arise from it.

 

5.7      No Partnership.  Except as otherwise expressly set forth herein, this Settlement does not and shall not be deemed to make any Party the agent for or partner of any other Party.

 

5.8      Reference to Regulations.  Any reference in this Settlement to any federal or state regulation shall be deemed to be a reference to such regulation, or successor regulation, in existence as of the date of the action.

 

5.9      Notice.  Except as otherwise provided in this paragraph, any Notice required by this Settlement shall be written.  It shall be sent to all Parties still in existence by first-class mail or comparable method of distribution, and shall be filed with FS and FERC.  For the Purpose of this Settlement, a Notice shall be effective 7 days after the date on which it is mailed or otherwise distributed.  When this Settlement requires Notice in less than 7 days, Notice shall be provided by telephone, facsimile or electronic mail and shall be effective when provided.  For the purpose of Notice, the list of authorized representatives of the Parties as of the Effective Date is attached as Appendix C.  The Parties shall provide Notice of any change in the authorized representatives designated in Appendix C; and Licensee shall maintain the current distribution list of such representatives.

 

5.10      Paragraph Titles for Convenience Only.  The titles for the paragraphs of this Settlement are used only for convenience of reference and organization, and shall not be used to modify, explain, or interpret any of the provisions of this Settlement or the intentions of the Parties. 

 

 

6.            Execution of Settlement

 

6.1        Signatory Authority.  Each signatory to this Settlement certifies that he or she is authorized to execute this Settlement and to legally bind the Party he or she represents, and that such Party shall be fully bound by the terms hereof upon such signature without any further act, approval, or authorization by such Party.

 

          6.1.1        Initialing by FWS.  By initialing this Settlement, FWS signifies its agreement to this Settlement subject to review of the effects of this Settlement under Section 7 of ESA on species listed or proposed for listing under that law.  Provided FWS issues a non-jeopardy biological opinion at the conclusion of the Section 7 consultation that is consistent with this Settlement, FWS agrees to become at that time signatory to this Settlement.

 

6.2      Disclosure of Other Agreements.  Except for the 1991 Fish and Wildlife Agreement, each Party represents that it is not a party to any other existing agreement with any Party or non-Party relating to this Settlement.  If a Party subsequently determines that it has such an agreement, such Party shall provide Notice of the terms of that agreement.

 

6.3      Signing in Counterparts.  This Settlement may be executed in any number of counterparts, and each executed counterpart shall have the same force and effect as an original instrument as if all the signatory Parties to all of the counterparts had signed the same instrument.  Any signature page of this Settlement may be detached from any counterpart of this Settlement without impairing the legal effect of any signatures thereon, and may be attached to another counterpart of this Settlement identical in form hereto but having attached to it one or more signature pages.

 

WHEREFORE, for valuable consideration, which is hereby acknowledged, and by authorized representatives, the Parties execute this Settlement effective as of September 18, 2000.


Pacific Gas and Electric Company

 

_________________________________________

by _______________________________________

         (Print)                   (Title)

 

 

United States Department of Agriculture Forest Service

 

__________________________________________

by ________________________________________

         (Print)                   (Title)

 

 

United States Department of the Interior Fish and Wildlife Service

 

_____ (intitial)

by ________________________________________

         (Print)                     (Title)

__________________________________________ (signature)

by ________________________________________

         (Print)                   (Title)

 

 

California Department of Fish and Game

 

____________________________________________

by __________________________________________

         (Print)                   (Title)

 

 

California State Water Resources Control Board

 

_____________________________________________

by ___________________________________________

         (Print)                   (Title)

 

 

Natural Heritage Institute

 

_____________________________________________

by ___________________________________________

         (Print)                   (Title)


Friends of the River

 

______________________________________________

by ____________________________________________

         (Print)                   (Title)

 

 

Plumas County

 

_______________________________________________

by _____________________________________________

         (Print)                   (Title)

 

 

California Outdoors

 

________________________________________________

by ______________________________________________

         (Print)                   (Title)

 

 

California Trout

 

_________________________________________________

by _______________________________________________

         (Print)                   (Title)

 

 

Chico Paddleheads

 

___________________________________________________

by _________________________________________________

         (Print)                   (Title)

 


American Whitewater

 

_______________________________________________

by _____________________________________________

         (Print)                   (Title)

 

 

Shasta Paddlers

 

______________________________________________

by ___________________________________________

         (Print)                   (Title)

 

 


Relicensing Settlement Agreement

Appendix A

 

 

Protection, Mitigation and Enhancement Measures Recommended to be Included in the New Project License and FS Final 4(e) Conditions and Used in Other Regulatory Approvals

 

Section I. Water Temperature

 

1.  Water Temperature Requirement.  In order to reasonably protect cold freshwater habitat, Licensee shall maintain mean daily water temperatures of 20 degrees Celsius or less in the Rock Creek and Cresta Reaches, to the extent that Licensee can reasonably control such temperatures.  Reasonable Control Measures are: the flow schedules stated in Section II, Table A below and implementation of the measures stated in this Section I.  Further measures to maintain mean daily water temperatures of 20 degrees Celsius or less in the Rock Creek and Cresta Reaches may be required by subsequent amendment of the New Project License under FERC’s reservation of authority as provided in Paragraph 6 below.

 

2.  Prattville Intake Control Measure.  Licensee shall, within three months after issuance of a New Project License, initiate a modeling study to evaluate the anticipated effectiveness of the Prattville Intake Modification control measures.  The study shall be completed as soon as practicable but no later than one year after issuance of New Project License.  The ERC and FS will evaluate the effectiveness of such control measures after review of the study results.

 

Subject to the provisions of Paragraph 5 below which sets forth the Licensee’s total financial commitment for Reasonable Control Measures as set forth in Paragraphs 2 and 4 of this section, the ERC and FS shall affirmatively determine which Prattville Intake Modification control measures, if any, shall be implemented. This determination shall be based on a finding that the modification control measures will effectively contribute to the maintenance of mean daily water temperatures of 20 degrees Celsius or less in the Rock Creek and Cresta Reaches.  This determination shall also be based on the best scientific information available, the use of sound scientific methods,  consideration of the relative cost of different Prattville Intake Modification control measures, and the relative temperature control benefits of such measures and alternatives thereto.

 

Licensee shall construct any Prattville Intake Modifications and commence operation for selective withdrawal of coldwater from Lake Almanor no later than one winter and one following summer season after issuance of the New Project License and the affirmative determination of the ERC and FS above, unless that schedule is impractical due to any further regulatory approval required for such control measures.  In the event that further regulatory approval is required, Licensee shall promptly apply for such approval, and shall implement the control measures no later than one winter and one following summer season after obtaining the requisite approval.

 

3.  Water Temperature Monitoring.  Licensee shall implement a water temperature monitoring program.  The program shall continue for no less than five years after installation of the Prattville Intake Modification, or five years after a determination pursuant to Paragraph 2 of this section that the Prattville Intake Modification will be ineffective and therefore should not be constructed.  During the term of the New Project License, the monitoring and reporting requirements set forth herein may be reduced or terminated after it is demonstrated to the satisfaction of the ERC and the FS that mean daily temperatures of 20 degrees Celsius or less have been and will be achieved, or that a given requirement is not necessary to determine whether this temperature objective will be met.

 

The temperature monitoring program shall consist of continuous temperature and flow monitoring in the Rock Creek, Cresta, Belden and Seneca reaches, along with temperature monitoring in their major tributaries, from June 1 through September 30, at the sites designated below for 15 years following issuance of  the New Project License.  Continuous temperature monitoring shall be conducted at gages NF 57 below Rock Creek and NF 56 below Cresta, from June 1 through October 31, for the term of the New Project License.  Flow monitoring shall be conducted at existing flow gages.

 

Temperature monitoring data will be used to develop and verify a model that predicts, with reasonable accuracy, the temperature profile of the river based on data from NF 56 and NF 57.  Once the temperature model has been determined by the ERC and FS to be reasonably accurate for determining downstream temperature, the ERC and FS may reduce the number of non-telemetered sites or the frequency of reporting data.

 

Monitoring sites in Rock Creek and Cresta Reaches shall be located as follows:

 

Rock Creek Reach:

NFFR below Rock Creek Dam

NFFR at the NF57 gage (data telemetered to Rock Creek PH)

NFFR above Bucks Creek

Chips Creek

Milk Ranch Creek

Chambers Creek

Jackass Creek

Bucks Creek

Bucks PH Tailrace

NFFR above Rock Creek PH

Rock Creek PH Tailrace

 


Cresta Reach:

NFFR below Cresta Dam

NFFR at the NF56 gage (data telemetered to Rock Creek PH)

NFFR above Cresta PH

Rock Creek

Grizzly Creek.

 

If monitoring results from gages NF 57 and NF 56 demonstrate that mean daily water temperatures regularly exceed 20 degrees Celsius in the Rock Creek or Cresta reaches in October, the Licensee shall monitor at the following sites in October:  NFFR below Rock Creek Dam; NFFR above Bucks Creek; NFFR above Rock Creek PH; NFFR below Cresta Dam; and NFFR above Cresta PH.  The temperature monitoring program also shall include continuous water temperature monitoring at a reasonably accessible site on the Middle Fork Feather River, for the period June 1 through September 30.  In addition, Licensee shall monitor water temperature profiles in Lake Almanor and Butt Valley Reservoir, and collect other data (e.g., water velocity measurements) as needed to evaluate the efficacy of temperature control measures, for the period June 1 through September 30.  Finally, Licensee shall maintain two meteorology monitoring stations, one at the Project and another at Project No. 2105, at which data shall be collected for the period May 1 through October 31.  License shall provide the meteorological data to any member of the ERC or FS upon request.

 

Licensee shall provide monitoring results for 9 years of the first 15 years after issuance of a New Project License to the ERC and the FS on a weekly basis in dry or critically dry water years, or bi-weekly in normal and wet water years, for the following monitoring sites: NFFR below Rock Creek Dam; NFFR at the NF 57 gage; NFFR above Bucks Creek; NFFR above Rock Creek PH; NFFR below Cresta Dam; NFFR at the NF 56 gage; and NFFR above Cresta PH.  The ERC and FS shall determine which 9 years these monitoring results shall be collected and provided to them.  This determination shall be made by the ERC and FS by May 1 of each year.  Reporting of these monitoring results to the ERC and FS shall be undertaken in a reasonable manner and form to be specified in the temperature monitoring plan required below.  In addition to the foregoing, reporting of continuous temperature monitoring results from NF 56 and NF 57 gages shall be made available to any member of the ERC or FS upon request for the term of New Project License.

 

If water temperatures monitored at NF 56 or NF 57 exceed a mean daily average of 20 degrees Celsius for two consecutive days, Licensee shall provide notice to the ERC and FS.  The Licensee shall inform the ERC and FS of any actions being taken by the Licensee to maintain water temperatures at a mean daily average of 20 degrees Celsius or less.  Analysis of the effectiveness of these actions shall be included in the annual Monitoring Report.

 

The Licensee shall submit to FERC an annual Monitoring Report that includes all monitoring results for the prior year and analyzes the effectiveness of the control measures in achieving mean daily temperatures of 20 degrees Celsius or less in the Rock Creek and Cresta Reaches.  The report shall be submitted no later than May 31 of each yearThe Monitoring Report shall be prepared in consultation with the ERC and FS and shall be provided to them on submittal.

 

Licensee shall prepare a water temperature monitoring plan which provides for implementation (including a schedule for implementation) of the temperature monitoring program described above.  The plan shall be prepared in consultation with the ERC and FS.  As soon as practicable but not later than one year after issuance of the New Project License, Licensee shall file the plan with the SWRCB for approval.  Licensee shall thereafter submit the plan to FERC for approval.  If FERC modifies the plan as submitted, the Licensee shall comply with the plan as approved by FERC.

 

4.  Additional Reasonable Control Measures.  Within five years of the date when the Commission approves the water temperature monitoring plan, the Licensee shall prepare a report that evaluates whether mean daily temperatures of 20 degrees Celsius or less have been and will be achieved in the Rock Creek and Cresta Reaches, and if not, whether additional reasonable control measures are available.  The report shall include recommendations for the implementation of any such measures. 

 

The report shall include all modeling and monitoring results required by Paragraph 2 and 3 above.  It shall also factor in economic considerations in evaluating whether additional temperature control measures are reasonable.

 

Subject to the provisions of Paragraph 5 below which sets forth the Licensee’s total financial commitment for Reasonable Control Measures as set forth in Paragraphs 2 and 4 of this section, the ERC and FS shall make an affirmative determination whether additional temperature control measures shall be implemented.  This affirmative determination shall be based on the best scientific information available, the use of sound scientific methods, consideration of the relative cost of different control measures, and other relevant factors.  As soon as practicable after such affirmative determination, Licensee shall implement any additional reasonable control measures for which no further regulatory approval is necessary.  Licensee shall promptly apply for regulatory approval for any other additional reasonable control measures that the ERC and FS affirmatively determine shall be implemented.

 

5.  Coldwater Habitat and Fishery Mitigation and Enhancement Fund (Fund).  On issuance of the New Project License, Licensee shall establish a tracking account and fund a total of $5,000,000 (current dollars) for expenditure on water temperature control measures.  Seventy-five months after such issuance of the New Project License, Licensee shall add to the Fund an additional amount not to exceed $2,000,000 (January 2001 dollars, escalated per Paragraph 4.5.5 of this Settlement), provided the ERC and FS make an affirmative determination, based on the first 5 years of monitoring results, that further measures are necessary to maintain mean daily water temperatures of 20 degrees Celsius in the Rock Creek and Cresta Reaches, and that the additional funding is appropriate for this purpose.  The balance in the Fund shall accrue interest at the 90-day commercial paper rate as published by the Federal Reserve Bank of New York, credited on a quarterly basis.

 

The primary purpose of the Fund shall be the temperature control measures described in Paragraphs 2 and 4 of this section, exclusive of the development and implementation of the temperature monitoring plan pursuant to Paragraph 3 of this section.  The Fund may be used to undertake other measures that directly enhance coldwater habitat and fishery in the Rock Creek and Cresta Reaches, if the ERC and FS determine that further expenditure on temperature control measures will not be effective in maintaining a mean daily water temperatures of 20 degrees Celsius or less in these reaches.  The Fund shall not be used, however, to compensate the Licensee for foregone power generation due to flow schedules stated in Section II, Table A below.  The Fund may be used to purchase additional flow only if the ERC has determined that no other reasonable temperature control measures are available.

 

Decisions on expenditures to be charged to the Fund shall be made by the ERC and FS.  Such decisions shall be based on the best scientific information available and the use of sound scientific methods.  No expenditure shall be made and charged to the Fund in absence of any necessary regulatory or other legal approval, or for actions that would be in conflict with any regulatory, legal, or contractual requirement.

 

All temperature control measures identified pursuant to Paragraphs 2 and 4 of this section shall be funded from the Fund.  If the Prattville Intake Modification is determined to be the Submerged Curtain/Skimmer Wall pursuant to Paragraph 2 of this section, Licensee shall debit the Fund $3,000,000 for the cost of its design and construction. Licensee shall retain any difference between $3,000,000 and the actual design and construction cost of the Submerged Curtain/Skimmer Wall.  Any design and construction costs in excess of $3,000,000 and future operation and maintenance costs will not be debited from the Fund.

 

Any unallocated Fund balance after the New Project License expiration plus the term(s) of any annual license(s), which may be issued after license expiration or license surrender shall revert back to Licensee.  Licensee shall distribute an accounting statement to FERC, ERC and the FS within 30 days after January 1 of each year after the Fund is established, summarizing the Fund balance, accrued interest, and previous charged amounts.  Licensee shall administer all work and payments under the Fund in a manner consistent with its normal business practices.  Licensee’s cost of administering the Fund account shall not be charged to the Fund.

 

Funding under this paragraph may be used in conjunction with funds that may be available from other sources, including but not limited to Licensee’s other relicensing proceedings on the NFFR.

 

6.  Reservation of FERC Authority.  FERC reserves authority to reopen for cause the New Project License to protect Beneficial Uses of the NFFR through coordinated operations of this Project, North Fork Feather Project (No. 2105) and Poe Project (No. 2107).  Such reopener may occur in conjunction with the relicensing proceedings for Nos. 2105 and 2107.

 

 

 

Section II. River Flow Management

 

1.  Minimum River Flows.  For the preservation and improvement of fisheries resources in the Project area, Licensee shall maintain specified Minimum River Flows and Pulse Flows below Project dams as measured at gages NF-56 and NF-57 in accordance with Table A below.  Table A provides for adjustments in flow releases over the term of the license.  Minimum River Flows at the levels specified in the first 5-year period shall be initiated within 60 days of issuance of a New Project License.  The first official test year shall begin on the January 1 of the year following issuance of a New Project License.  Test years shall be on a calendar year basis and the first 5-year test period shall last until December 31 of the fifth full year after issuance of a New Project License.  On January 1 of the sixth full year after issuance of a New Project License the Minimum River Flows shall increase automatically to the levels of the second 5-year period.  Minimum River Flows shall be maintained at the second 5-year level for a five year test period provided at least four consecutive non-critically dry years occur.  If the test period is interrupted by one or more critically dry years the test period shall be extended as determined by the ERC and FS.  Adjustments to required Minimum River Flows after the completion of the second 5-year test period shall be made as specified by the ERC and  FS.  Such adjustments shall not exceed the Cap Flows applicable for the third 5-year test period.  The length of the third 5-year test period shall be subject to the same conditions as the second 5-year test period (may be extended by the ERC and FS in the event critically dry years occur).  Adjustments after the third 5-year test period shall be as specified by the ERC and FS, and such adjustments shall not exceed the Cap Flows applicable for the third 5-year test period.  FERC shall be advised of the status of the test periods in the ERC’s annual report.


Table A.1

 

 

Rock Creek Reach Minimum River Flow, Pulse, and Ramping

 

First 5-Year Flow Period - Normal & Wet Years

 

 

 

Season

Month

Base Flow (cfs) (5)

Pulse (cfs) (6)

Ramping Rate

(cfsD/hr)

Block Loading

Boating Flow (cfs)

Launch Window

Spring

Mar

250

2 @ >1600

rise & fall from EBF (1)

Belden (3)

-

-

 

Apr

250

2 @ >1600

rise & fall from EBF (1)

Belden (3)

-

-

 

May

250

2 @ >1600

rise & fall from EBF (1)

Belden (3)

-

-

Summer & Fall

Jun

220

1 @ >1000 (2)

300/400 cfs rise/150 cfs fall (4)

Belden (3)

1600

10 - 4 pm

 

Jul

180

0

400 cfs rise/150 cfs fall

no

1200

10 - 4 pm

 

Aug

180

0

400 cfs rise/150 cfs fall

no

1000

10 - 4 pm

 

Sep

180

0

400 cfs rise/150 cfs fall

no

1000

10 - 4 pm

 

Oct

180

0

400 cfs rise/150 cfs fall

no

1000

10 - 4 pm

 

Nov

180

0

400 cfs rise/150 cfs fall

no

-

-

Winter

Dec

200

0

400 cfs rise/150 cfs fall

no

-

-

 

Jan

225

0

400 cfs rise/150 cfs fall

no

-

-

 

Feb

225

0

400 cfs rise/150 cfs fall

no

-

-

Notes:

(1)  Rise and fall to follow E. Branch Feather rate, to be achieved by holding Belden and Rock Creek PHs constant during pulse (unless RCPH decreased to maintain flow > target pulse).  Pulse event can be terminated when EBF flow is constant (+-100 cfs/hr), at which time normal operations resume, and spill may be reduced at 150 cfs/hr. Same rise and fall ramping limitations apply to non-pulse spill events past diversion dam between March and first 2 weeks of June.

(2)  In first 2 weeks of June, a pulse of 1000 cfs (from EBF or supplemented) of at least 12 continuous hours in duration should occur, assuming flows at NF57 are not already >3000 cfs.

(3)  If flows at NF57 are between 275 and 3000 cfs, Belden will be block loaded to avoid having spills start and stop at Rock Creek Reservoir.

(4)  300 cfs/hr rise during first 2 weeks of June, 400 cfs/hr rise for second 2 weeks of June if spill is from operations.

(5)  Minimum monthly flow to be measured at Licensee gage NF57.

(6)  Pulses are 12 hrs continuous duration, and no riparian flows occur.

 

 


Table A.1 (continued)

 

 

Rock Creek Reach Minimum River Flow, Pulse, and Ramping

First 5-Year Flow Period - Dry Years

 

Season

Month

Base Flow (cfs) (5)

Pulse (cfs) (6)

Ramping Rate

(cfsD/hr)

Block Loading

Boating Flow (cfs)

Launch Window

 

Spring

Mar

200

2 @ >1000

rise & fall from EBF (1)

Belden (3)

-

-

 

 

Apr

200

2 @ >1000

rise & fall from EBF (1)

Belden (3)

-

-

 

 

May

200

0

rise & fall from EBF (1)

Belden (3)

-

-

 

Summer & Fall

Jun

175

0

300/400 cfs rise/150 cfs fall (4)

no

1000

10 - 1 pm

 

 

Jul

150

0

400 cfs rise/150 cfs fall

no

800

10 - 1 pm

 

 

Aug

150

0

400 cfs rise/150 cfs fall

no

800

10 - 1 pm

 

 

Sep

150

0

400 cfs rise/150 cfs fall

no

800

10 - 1 pm

 

 

Oct

150

0

400 cfs rise/150 cfs fall

no

-

-

 

 

Nov

150

0

400 cfs rise/150 cfs fall

no

-

-

 

Winter

Dec

160

0

400 cfs rise/150 cfs fall

no

-

-

 

 

Jan

180

0

400 cfs rise/150 cfs fall

no

-

-

 

 

Feb

180

0

400 cfs rise/150 cfs fall

no

-

-

 

Notes: 

(1)  Rise and fall to follow E. Branch Feather rate, to be achieved by holding Belden and Rock Creek PHs constant during pulse (unless RCPH decreased to maintain flow > target pulse).  Pulse event can be terminated when EBF flow is constant (+-100 cfs/hr), at which time normal operations resume, and spill may be reduced at 150 cfs/hr. Same rise and fall ramping limitations apply to non-pulse spill  events past diversion between March and end of May.

(3)  If flows at NF57 are between 275 and 3000 cfs, Belden will be block loaded to avoid having spills start and stop at Rock Creek Reservoir.

(4)  300 cfs/hr rise during first 2 weeks of June, 400 cfs/hr rise for second 2 weeks of June if spill is from operations.

(5)  Minimum monthly flow to be measured at Licensee gage NF57.

(6)  Pulses are 12 hrs continuous duration, and no riparian flows occur.


Table A.1 (continued)

 

Rock Creek Reach Minimum River Flow, Pulse, and Ramping

First 5-Year Flow Period - Critically Dry Years

 

Season

Month

Base Flow (cfs) (5)

Pulse (cfs) (6)

Ramping Rate

(cfsD/hr)

Block Loading

Boating Flow (cfs)

Launch Window

 

Spring

Mar

110

1 @ >1000

rise & fall from EBF (1)

Belden (3)

-

-

 

 

Apr

110

1 @ >1000

rise & fall from EBF (1)

Belden (3)

-

-

 

 

May

150

0

rise & fall from EBF (1)

Belden (3)

-

-

 

Summer & Fall

Jun

150 (7)

0

300/400 cfs rise/150 cfs fall (4)

no

1000

10 - 1 pm

 

 

Jul

150 (7)

0

400 cfs rise/150 cfs fall

no

800

10 - 1 pm

 

 

Aug

150 (7)

0

400 cfs rise/150 cfs fall

no

800

10 - 1 pm

 

 

Sep

150 (7)

0

400 cfs rise/150 cfs fall

no

800

10 - 1 pm

 

 

Oct

150 (7)

0

400 cfs rise/150 cfs fall

no

-

-

 

 

Nov

110

0

400 cfs rise/150 cfs fall

no

-

-

 

Winter

Dec

110

0

400 cfs rise/150 cfs fall

no

-

-

 

 

Jan

110

0

400 cfs rise/150 cfs fall

no

-

-

 

 

Feb

110

0

400 cfs rise/150 cfs fall

no

-

-

 

Notes: 

(1)  Rise and fall to follow E. Branch Feather rate, to be achieved by holding Belden and Rock Creek PHs constant during pulse (unless RCPH decreased to maintain flow > target pulse).  Pulse event can be terminated when EBF flow is constant (+-100 cfs/hr), at which time normal operations resume, and spill may be reduced at 150 cfs/hr

(3)  if flows at NF57 are between 275 and 3000 cfs, Belden will be block loaded to avoid having spills start and stop at Rock Creek Reservoir.

(4)  300 cfs/hr rise during first 2 weeks of June, 400 cfs/hr rise for second 2 weeks of June if spill is from operations.

(5)  Minimum monthly flow to be measured at Licensee gage NF57.

(6)  Pulses are 12 hrs continuous duration, and no riparian flows occur.

(7)  The base flow of 150 cfs shall be increased to 200 cfs, or to any flow between 150 and 200 cfs, to the extent necessary to contribute to the maintenance of mean daily temperatures of 20 degrees Celsius or less in the Rock Creek Reach.  Similarly, this increased flow shall be reduced back to the 150 cfs base flow when not required to maintain mean daily temperatures of 20 degrees Celsius in the Rock Creek Reach.  For the first three years after issuance of a New Project license, or until a temperature model as referred to in Section I, Paragraph 3 is developed, Licensee shall use the mean daily water temperature measured at NF 57 to determine whether and how to implement this flow provision.  This flow provision shall not apply, and the base flow shall remain at 150 cfs, if the ERC and FS determine, based on a review of temperature monitoring results or by assessment from a reasonably accurate water temperature model, that the increase in base flows will not result in a reduction in water temperature New Project beneficial to cold freshwater habitat, or the cost of the increase in base flow is dramatically disproportional to the benefit.  To implement this flow provision, Licensee shall, in consultation with the ERC and FS, submit to FERC for approval, as soon as practicable but no later than one year after issuance of a license, a Critically Dry Year Flow Operations and Compliance Plan.  The plan shall establish reasonable procedures and criteria to support maintenance of mean daily water temperatures of 20 degrees Celsius.  These procedures and criteria shall be similar for both increasing flows up to 200 cfs (or any flow between 150 and 200 cfs) and decreasing flows back to 150 cfs.


Table A.1 (continued)

 

 

Cresta Reach Minimum River Flow, Pulse, and Ramping

First 5-Year Flow Period - Normal & Wet Years

 

Season

Month

Base Flow (cfs) (5)

Pulse (cfs) (6)

Ramping Rate

(cfsD/hr)

Block Loading

Boating Flow (cfs)

Launch Window

Spring

Mar

250

2 @ >1600

rise & fall from EBF (1)

Belden (3)

-

-

 

Apr

250

2 @ >1600

rise & fall from EBF (1)

Belden (3)

-

-

 

May

250

2 @ >1600

rise & fall from EBF (1)

Belden (3)

-

-

Summer & Fall

Jun

240

1 @ >1000 (2)

300/400 cfs rise/150 cfs fall (4)

Belden (3)

1600

10 - 4 pm

 

Jul

220

0

400 cfs rise/150 cfs fall

no

1200

10 - 4 pm

 

Aug

220

0

400 cfs rise/150 cfs fall

no

1000

10 - 4 pm

 

Sep

220

0

400 cfs rise/150 cfs fall

no

1000

10 - 4 pm

 

Oct

220

0

400 cfs rise/150 cfs fall

no

1000

10 - 4 pm

 

Nov

220

0

400 cfs rise/150 cfs fall

no

-

-

Winter

Dec

240

0

400 cfs rise/150 cfs fall

no

-

-

 

Jan

240

0

400 cfs rise/150 cfs fall

no

-

-

 

Feb

240

0

400 cfs rise/150 cfs fall

no

-

-

Note: 

(1)  Rise and fall to follow E. Branch Feather rate, to be achieved by holding Belden, Rock Creek, & Cresta PHs constant during pulse (unless Cresta PH decreased to maintain flow > target pulse).  Pulse event can be terminated when EBF flow is constant (+-100 cfs/hr), at which time normal operations resume, and spill may be reduced at 150 cfs/hr. Same rise and fall ramping limitations apply to non-pulse spill events past diversion dam between March and first 2 weeks of June.

(2)  In first 2 weeks of June, a pulse of 1000 cfs (from EBF or supplemented) of at least 12 continuous hours in duration should occur, assuming flows at NF56 are not already > 3000 cfs.

(3)  If flows at NF56 are between 275 and 3000 cfs, Belden & Rock Creek will be block loaded to avoid having spills start and stop at Cresta Reservoir.

(4)  300 cfs/hr rise during first 2 weeks of June, 400 cfs/hr rise for second 2 weeks of June if spill is from operations.

(5)  Minimum monthly flow to be measured at Licensee gage NF56, and at least 100 cfs will be released from Cresta Diversion Dam at all times.

(6)  Pulses are 12 hrs continuous duration, and no riparian flows occur.

 


Table A.1. (continued)

 

 

Cresta Reach Minimum River Flow, Pulse, and Ramping

First 5-Year Flow Period - Dry Years

 

Season

Month

Base Flow (cfs) (5)

Pulse (cfs) (6)

Ramping Rate

(cfsD/hr)

Block Loading

Boating Flow (cfs)

Launch Window

Spring

Mar

200

2 @ >1000

rise & fall from EBF (1)

Belden (3)

-

-

 

Apr

200

2 @ >1000

rise & fall from EBF (1)

Belden (3)

-

-

 

May

200

0

rise & fall from EBF (1)

Belden (3)

-

-

Summer & Fall

Jun

190

0

300/400 cfs rise/150 cfs fall  (4)

no

1000

10 - 1 pm

 

Jul

175

0

400 cfs rise/150 cfs fall

no

800

10 - 1 pm

 

Aug

175

0

400 cfs rise/150 cfs fall

no

800

10 - 1 pm

 

Sep

175

0

400 cfs rise/150 cfs fall

no

800

10 - 1 pm

 

Oct

175

0

400 cfs rise/150 cfs fall

no

-

-

 

Nov

175

0

400 cfs rise/150 cfs fall

no

-

-

Winter

Dec

190

0

400 cfs rise/150 cfs fall

no

-

-

 

Jan

190

0

400 cfs rise/150 cfs fall

no

-

-

 

Feb

190

0

400 cfs rise/150 cfs fall

no

-

-

Notes: 

(1)  Rise and fall to follow E. Branch Feather rate, to be achieved by holding Belden, Rock Creek, & Cresta PHs constant during pulse (unless Cresta PH decreased to maintain flow > target pulse).  Pulse event can be terminated when EBF flow is constant (+-100 cfs/hr), at which time normal operations resume, and spill may be reduced at 150 cfs/hr. Same rise and fall ramping limitations apply to non-pulse spill events past diversion during March - first 2 weeks of June.

(3)  If flows at NF56 are between 225 and 3000 cfs, Belden & Cresta will be block loaded to avoid having spills start and stop at Cresta Reservoir.

(4)  300 cfs/hr rise during first 2 weeks of June, 400 cfs/hr rise for second 2 weeks of June if spill is from operations.

(5)  Minimum monthly flow to be measured at Licensee gage NF56, and at least 100 cfs will be released from Cresta Diversion Dam at all times.

(6)  Pulses are 12 hrs continuous duration, and no riparian flows occur.

 

 


Table A.1 (continued)

 

 

Cresta Reach Minimum River Flow, Pulse, and Ramping

First 5-Year Flow Period - Critically Dry Years

 

Season

Month

Base Flow (cfs) (5)

Pulse (cfs) (6)

Ramping Rate

(cfsD/hr)

Block Loading

Boating Flow (cfs)

Launch Window

Spring

Mar

100

1 @ >1000

rise & fall from EBF (1)

Belden (3)

-

-

 

Apr

100

1 @ >1000

rise & fall from EBF (1)

Belden (3)

-

-

 

May

140

0

rise & fall from EBF (1)

Belden (3)

-

-

Summer &Fall

Jun

140 (7)

0

300/400 cfs rise/150 cfs fall (4)

no

1000

10 - 1 pm

 

Jul

140 (7)

0

400 cfs rise/150 cfs fall

no

800

10 - 1 pm

 

Aug

140 (7)

0

400 cfs rise/150 cfs fall

no

800

10 - 1 pm

 

Sep

140 (7)

0

400 cfs rise/150 cfs fall

no

800

10 - 1 pm

 

Oct

140 (7)

0

400 cfs rise/150 cfs fall

no

-

-

 

Nov

100

0

400 cfs rise/150 cfs fall

no

-

-

Winter

Dec

100

0

400 cfs rise/150 cfs fall

no

-

-

 

Jan

100

0

400 cfs rise/150 cfs fall

no

-

-

 

Feb

100

0

400 cfs rise/150 cfs fall

no

-

-

Notes: 

(1)  Rise and fall to follow E. Branch Feather rate, to be achieved by holding Belden, Rock Creek, & Cresta PHs constant during pulse (unless Cresta PH decreased to maintain flow > target pulse).  Pulse event can be terminated when EBF flow is constant (+-100 cfs/hr), at which time normal operations resume, and spill may be reduced at 150 cfs/hr.

(3)  If flows at NF56 are between 225 and 3000 cfs, Belden & Cresta will be block loaded to avoid having  spills start and stop at Cresta Reservoir.

(4)  300 cfs/hr rise during first 2 weeks of June, 400 cfs/hr rise for second 2 weeks of June if spill is from operations.

(5)   Minimum monthly flow to be measured at Licensee gage NF56, and at least 100 cfs will be released from Cresta Diversion Dam at all times.

(6)   Pulses are 12 hrs continuous duration, and no riparian flows occur.

(7)  The base flow of 140 cfs shall be increased to 200 cfs, or to any flow in between 140 and 200 cfs, to the extent necessary to contribute to the maintenance of mean daily temperatures of 20 degrees Celsius or less in the Cresta Reach.  Similarly, this increased flow shall be reduced back to the 140 cfs base flow when not required to maintain mean daily temperatures of 20 degrees Celsius in the Cresta Reach.  For the first three years after issuance of a New Project license, or until a temperature model as referred to in Section I, paragraph 3 is developed, Licensee shall use the mean daily water temperature measured at NF 56 to determine whether and how to implement this provision.   This flow provision shall not apply, and the base flow shall remain at 140 cfs, if the ERC and FS determine, based on a review of temperature monitoring results or by assessment from a reasonably accurate water temperature model, that the increase in base flows will not result in a reduction in water temperature beneficial to cold freshwater habitat, or the cost of the increase in base flow is dramatically disproportional to the benefit.  To implement this flow provision, Licensee shall, in consultation with the ERC and FS, submit to FERC for approval, as soon as practicable but no later than one year after issuance of a New Project license, a Critically Dry Year Flow Operations and Compliance Plan.  The plan shall establish reasonable procedures and criteria to maintain mean daily water temperatures of 20 degrees Celsius.  These procedures and criteria shall be similar for both increasing flows up to 200 cfs (or any flow between 140 and 200 cfs) and decreasing flows back to 140 cfs.

 


Table A.2

 

 

Rock Creek Reach Minimum River Flow, Pulse, and Ramping

Second 5-Year Flow Period - Normal & Wet Years (8)

 

Season

Month

Base Flow (cfs) (5)

Pulse (cfs) (6)

Ramping Rate

(cfsD/hr)

Block Loading

Boating Flow (cfs)

Launch Window

Spring

Mar

350

2 @ >1600

rise & fall from EBF (1)

Belden (3)

-

-

 

Apr

350

2 @ >1600

rise & fall from EBF (1)

Belden (3)

-

-

 

May

350

2 @ >1600

rise & fall from EBF (1)

Belden (3)

-

-

Summer & Fall

Jun

260

1 @ >1000 (2)

300/400 cfs rise/150 cfs fall (4)

Belden (3)

1600

10 - 4 pm

 

Jul

260

0

400 cfs rise/150 cfs fall

no

1200

10 - 4 pm

 

Aug

260

0

400 cfs rise/150 cfs fall

no

1000

10 - 4 pm

 

Sep

260

0

400 cfs rise/150 cfs fall

no

1000

10 - 4 pm

 

Oct

260

0

400 cfs rise/150 cfs fall

no

1000

10 - 4 pm

 

Nov

260

0

400 cfs rise/150 cfs fall

no

-

-

Winter

Dec

350

0

400 cfs rise/150 cfs fall

no

-

-

 

Jan

350

0

400 cfs rise/150 cfs fall

no

-

-

 

Feb

350

0

400 cfs rise/150 cfs fall

no

-

-

Notes:,

(1)  Rise and fall to follow E. Branch Feather rate, to be achieved by holding Belden and Rock Creek PHs constant during pulse (unless RCPH decreased to maintain flow > target pulse).  Pulse event can be terminated when EBF flow is constant (+-100 cfs/hr), at which time normal operations resume, and spill may be reduced at 150 cfs/hr. Same rise and fall ramping limitations apply to non-pulse spill  events past diversion dam during March - first 2 weeks of June.

(2)  In first 2 weeks of June, a pulse of 1000 cfs (from EBF or supplemented) of at least 12 continuous hours in duration should occur, assuming flows at NF57 are not already> 3000 cfs.

(3)  If flows at NF57 are between 275 and 3000 cfs, Belden will be block loaded to avoid having spills start and stop at Rock Creek Reservoir.

(4)  300 cfs/hr rise during first 2 weeks of June, 400 cfs/hr rise for second 2 weeks of June if spill is from operations.

(5)  Minimum monthly flow to be measured at Licensee gage NF57.

(6)  Pulses are 12 hrs continuous duration, and no riparian flows occur.

(8)          Implementation of flow in this table is automatic after first 5 years.


Table A.2 (continued)

 

 

Rock Creek Reach Minimum River Flow, Pulse, and Ramping

Second 5-Year Flow Period - Dry Years (8)

 

Season

Month

Base Flow (cfs) (5)

Pulse (cfs) (6)

Ramping Rate

(cfsD/hr)

Block Loading

Boating Flow (cfs)

Launch Window

Spring

Mar

280

2 @ >1000

rise & fall from EBF (1)

Belden (3)

-

-

 

Apr

280

2 @ >1000

rise & fall from EBF (1)

Belden (3)

-

-

 

May

280

0

rise & fall from EBF (1)

Belden (3)

-

-

Summer & Fall

Jun

210

0

300/400 cfs rise/150 cfs fall (4)

no

1000

10 - 1 pm

 

Jul

210

0

400 cfs rise/150 cfs fall

no

800

10 - 1 pm

 

Aug

210

0

400 cfs rise/150 cfs fall

no

800

10 - 1 pm

 

Sep

210

0

400 cfs rise/150 cfs fall

no

800

10 - 1 pm

 

Oct

210

0

400 cfs rise/150 cfs fall

no

-

-

 

Nov

210

0

400 cfs rise/150 cfs fall

no

-

-

Winter

Dec

280

0

400 cfs rise/150 cfs fall

no

-

-

 

Jan

280

0

400 cfs rise/150 cfs fall

no

-

-

 

Feb

280

0

400 cfs rise/150 cfs fall

no

-

-

Notes:

(1)  Rise and fall to follow E. Branch Feather rate, to be achieved by holding Belden and Rock Creek PHs constant during pulse (unless RCPH decreased to maintain flow > target pulse).  Pulse event can be terminated when EBF flow is constant (+-100 cfs/hr), at which time normal operations resume, and spill may be reduced at 150 cfs/hr. Same rise and fall ramping limitations apply to non-pulse spill events past diversion dam during March - first 2 weeks of June.

(3)  If flows at NF57 are between 275 and 3000 cfs, Belden will be block loaded to avoid having spills start and stop at Rock Creek Reservoir.

(4)  300 cfs/hr rise during first 2 weeks of June, 400 cfs/hr rise for second 2 weeks of June if spill is from operations.

(5)  Minimum monthly flow to be measured at Licensee gage NF57.

(6)  Pulses are 12 hrs continuous duration, and no riparian flows occur.

(8)          Implementation of flow in this table is automatic after first 5 years.

 


Table A.2  (Continued)

 

 

Rock Creek Reach Minimum River Flow, Pulse, and Ramping

Second 5-Year Flow Period - Critically Dry Years

Season

Month

Base Flow (cfs) (5)

Pulse (cfs) (6)

Ramping Rate

(cfsD/hr)

Block Loading

Boating Flow (cfs)

Launch Window

Spring

Mar

110

1 @ >1000

rise & fall from EBF (1)

Belden (3)

-

-

 

Apr

110

1 @ >1000

rise & fall from EBF (1)

Belden (3)

-

-

 

May

150

0

rise & fall from EBF (1)

Belden (3)

-

-

Summer & Fall

Jun

150 (7)

0

300/400 cfs rise/150 cfs fall (4)

no

1000

10 - 1 pm

 

Jul

150 (7)

0

400 cfs rise/150 cfs fall

no

800

10 - 1 pm

 

Aug

150 (7)

0

400 cfs rise/150 cfs fall

no

800

10 - 1 pm

 

Sep

150 (7)

0

400 cfs rise/150 cfs fall

no

800

10 - 1 pm

 

Oct

150 (7)

0

400 cfs rise/150 cfs fall

no

-

-

 

Nov

110

0

400 cfs rise/150 cfs fall

no

-

-

Winter

Dec

110

0

400 cfs rise/150 cfs fall

no

-

-

 

Jan

110

0

400 cfs rise/150 cfs fall

no

-

-

 

Feb

110

0

400 cfs rise/150 cfs fall

no

-

-

Notes:

(1)  Rise and fall to follow E. Branch Feather rate, to be achieved by holding Belden and Rock Creek PHs constant during pulse (unless RCPH decreased to maintain flow > target pulse).  Pulse event can be terminated when EBF flow is constant (+-100 cfs/hr), at which time normal operations resume, and spill may be reduced at 150 cfs/hr.      

(3)  If flows at NF57 are between 275 and 3000 cfs, Belden will be block loaded to avoid having spills start and stop at Rock Creek Reservoir.     

(4)  300 cfs/hr rise during first 2 weeks of June, 400 cfs/hr rise for second 2 weeks of June if spill is from operations.

(5)  Minimum monthly flow to be measured at Licensee gage NF57.

(6)  Pulses are 12 hrs continuous  duration, and no riparian flows occur.

(7)  The base flow of 150 cfs shall be increased to 200 cfs, or to any flow between 150 and 200 cfs, to the extent necessary to contribute to the maintenance of mean daily temperatures of 20 degrees Celsius or less in the Rock Creek Reach.  Similarly, this increased flow shall be reduced back to the 150 cfs base flow when not required to maintain mean daily temperatures of 20 degrees Celsius in the Rock Creek Reach.  For the first three years after issuance of a New Project license, or until a temperature model as referred to in Section I, Paragraph 3 is developed, Licensee shall use the mean daily water temperature measured at NF 57 to determine whether and how to implement this flow provision.  This flow provision shall not apply, and the base flow shall remain at 150 cfs, if the ERC and FS determine, based on a review of temperature monitoring results or by assessment from a reasonably accurate water temperature model, that the increase in base flows will not result in a reduction in water temperature beneficial to cold freshwater habitat, or the cost of the increase in base flow is dramatically disproportional to the benefit.  To implement this flow provision, Licensee shall, in consultation with the ERC and FS, submit to FERC for approval, as soon as practicable but no later than one year after issuance of a New Project license, a Critically Dry Year Flow Operations and Compliance Plan.  The plan shall establish reasonable procedures and criteria to support maintenance of mean daily water temperatures of 20 degrees Celsius.  These procedures and criteria shall be similar for both increasing flows up to 200 cfs (or any flow between 150 and 200 cfs) and decreasing flows back to 150 cfs.

 


Table A.2  (Continued)

 

Cresta Reach Minimum River Flow, Pulse, and Ramping

Second 5-Year Flow Period - Normal & Wet Years (8)

Season

Month

Base Flow (cfs) (5)

Pulse (cfs) (6)

Ramping Rate

(cfsD/hr)

Block Loading

Boating Flow (cfs)

Launch Window

Spring

Mar

350

2 @ >1600

rise & fall from EBF (1)

Belden (3)

-

-

 

Apr

350

2 @ >1600

rise & fall from EBF (1)

Belden (3)

-

-

 

May

350

2 @ >1600

rise & fall from EBF (1)

Belden (3)

-

-

Summer & Fall

Jun

325

1 @ >1000 (2)

300/400 cfs rise/150 cfs fall (4)

Belden (3)

1600

10 - 4 pm

 

Jul

325

0

400 cfs rise/150 cfs fall

no

1200

10 - 4 pm

 

Aug

325

0

400 cfs rise/150 cfs fall

no

1000

10 - 4 pm

 

Sep

325

0

400 cfs rise/150 cfs fall

no

1000

10 - 4 pm

 

Oct

325

0

400 cfs rise/150 cfs fall

no

1000

10 - 4 pm

 

Nov

325

0

400 cfs rise/150 cfs fall

no

-

-

Winter

Dec

350

0

400 cfs rise/150 cfs fall

no

-

-

 

Jan

350

0

400 cfs rise/150 cfs fall

no

-

-

 

Feb

350

0

400 cfs rise/150 cfs fall

no

-

-

Notes:

(1)  Rise and fall to follow E. Branch Feather rate, to be achieved by holding Belden, Rock Creek, & Cresta PHs constant during pulse (unless Cresta PH decreased to maintain flow > target pulse).  Pulse event can be terminated when EBF flow is constant (+-100 cfs/hr), at which time normal operations resume, and spill may be reduced at 150 cfs/hr. Same rise and fall ramping limitations apply to non-pulse spill events past dam during March - first 2 weeks of June.

(2)  In first 2 weeks of June, a pulse of 1000 cfs (from EBF or supplemented) of at least 12 continuous hours in duration should occur, assuming flows at NF56 are not already > 3000 cfs.

(3)  If flows at NF56 are between 275 and 3000 cfs, Belden & Rock Creek will be block loaded to avoid having spills start and stop at Cresta Reservoir.

(4)  300 cfs/hr rise during first 2 weeks of June, 400 cfs/hr rise for second 2 weeks of June if spill is from operations.

(5)  Minimum monthly flow to be measured at Licensee gage NF56, and at least 100 cfs will be released from Cresta Diversion Dam at all times.

(6)  Pulses are 12 hrs continuous duration, and no riparian flows occur.

(8)          Implementation of flow in this table is automatic after first 5 years.

 


Table A.2  (Continued)

 

 

Cresta Reach Minimum River Flow, Pulse, and Ramping

Second 5-Year Flow Period - Dry Years (8)

Season

Month

Base Flow (cfs) (5)

Pulse (cfs) (6)

Ramping Rate

(cfsD/hr)

Block Loading

Boating Flow (cfs)

Launch Window

Spring

Mar

280

2 @ >1000

rise & fall from EBF(1)

Belden (3)

-

-

 

Apr

280

2 @ >1000

rise & fall from EBF(1)

Belden (3)

-

-

 

May

280

0

rise & fall from EBF(1)

Belden (3)

-

-

Summer

& Fall

Jun

260

0

300/400 cfs rise/150 cfs fall (4)

no

1000

10 - 1 pm

 

Jul

260

0

400 cfs rise/150 cfs fall

no

800

10 - 1 pm

 

Aug

260

0

400 cfs rise/150 cfs fall

no

800

10 - 1 pm

 

Sep

260

0

400 cfs rise/150 cfs fall

no

800

10 - 1 pm

 

Oct

260

0

400 cfs rise/150 cfs fall

no

-

-

 

Nov

260

0

400 cfs rise/150 cfs fall

no

-

-

Winter

Dec

280

0

400 cfs rise/150 cfs fall

no

-

-

 

Jan

280

0

400 cfs rise/150 cfs fall

no

-

-

 

Feb

280

0

400 cfs rise/150 cfs fall

no

-

-

Notes:

(1)  Rise and fall to follow E. Branch Feather rate, to be achieved by holding Belden, Rock Creek, & Cresta PHs  constant during pulse (unless Cresta PH decreased to maintain flow > target pulse).  Pulse  event can be terminated when EBF flow is constant (+-100 cfs/hr), at which time normal operations resume, and spill may be reduced at 150 cfs/hr. Same rise and fall ramping limitations apply to non-pulse spill  events past dam during March - first 2 weeks of June.     

(3)  If flows at NF56 are between 225 and 3000 cfs, Belden & Cresta will be block loaded to avoid having spills start and stop at Cresta Reservoir.     

(4)  300 cfs/hr rise during first 2 weeks of June, 400 cfs/hr rise for second 2 weeks of June if spill is from operations.     

(5)  Minimum monthly flow to be measured at Licensee gage NF56, and at least 100 cfs will be released from Cresta Diversion Dam at all times.      

(6)  Pulses are 12 hrs continuous duration, and no riparian flows occur.

(8)          Implementation of flow in this table is automatic after first 5 years.

 

 


Table A.2  (Continued)

 

 

Cresta Reach Minimum River Flow, Pulse, and Ramping

Second 5-Year Flow Period - Critically Dry Years

Season

Month

Base Flow (cfs) (5)

Pulse (cfs) (6)

Ramping Rate

(cfsD/hr)

Block Loading

Boating Flow (cfs)

Launch Window

Spring

Mar

100

1 @ >1000

rise & fall from EBF (1)

Belden (3)

-

-

 

Apr

100

1 @ >1000

rise & fall from EBF (1)

Belden (3)

-

-

 

May

140

0

rise & fall from EBF (1)

Belden (3)

-

-

Summer &Fall

Jun

140 (7)

0

300/400 cfs rise/150 cfs fall (4)

no

1000

10 - 1 pm

 

Jul

140 (7)

0

400 cfs rise/150 cfs fall

no

800

10 - 1 pm

 

Aug

140 (7)

0

400 cfs rise/150 cfs fall

no

800

10 - 1 pm

 

Sep

140 (7)

0

400 cfs rise/150 cfs fall

no

800

10 - 1 pm

 

Oct

140 (7)

0

400 cfs rise/150 cfs fall

no

-

-

 

Nov

100

0

400 cfs rise/150 cfs fall

no

-

-

Winter

Dec

100

0

400 cfs rise/150 cfs fall

no

-

-

 

Jan

100

0

400 cfs rise/150 cfs fall

no

-

-

 

Feb

100

0

400 cfs rise/150 cfs fall

no

-

-

Notes:

(1)  Rise and fall to follow E. Branch Feather rate, to be achieved by holding Belden, Rock Creek, & Cresta PHs constant during pulse (unless Cresta PH decreased to maintain flow > target pulse).  Pulse  event can be terminated when EBF flow is constant (+-100 cfs/hr), at which time normal operations resume, and spill may be reduced at 150 cfs/hr.      

(3)  If flows at NF56 are between 225 and 3000 cfs, Belden & Cresta will be block loaded to avoid having spills start and stop at Cresta Reservoir.     

(4)  300 cfs/hr rise during first 2 weeks of June, 400 cfs/hr rise for second 2 weeks of June if spill is from operations.     

(5)  Minimum monthly flow to be measured at Licensee gage NF56, and at least 100 cfs will be released from Cresta Diversion Dam at all times.      

(6)  Pulses are 12 hrs continuous duration, and no riparian flows occur.

(7)  The base flow of 140 cfs shall be increased to 200 cfs, or to any flow in between 140 and 200 cfs, to the extent necessary to contribute to the maintenance of mean daily temperatures of 20 degrees Celsius or less in the Cresta Reach.  Similarly, this increased flow shall be reduced back to the 140 cfs base flow when not required to maintain mean daily temperatures of 20 degrees Celsius in the Cresta Reach.  For the first three years after issuance of a New Project license, or until a temperature model as referred to in Section I, Paragraph 3 is developed, Licensee shall use the mean daily water temperature measured at NF 56 to determine whether and how to implement this provision.   This flow provision shall not apply, and the base flow shall remain at 140 cfs, if the ERC and FS determine, based on a review of temperature monitoring results or by assessment from a reasonably accurate water temperature model, that the increase in base flows will not result in a reduction in water temperature beneficial to cold freshwater habitat, or the cost of the increase in base flow is dramatically disproportional to the benefit.  To implement this flow provision, Licensee shall, in consultation with the ERC and FS, submit to FERC for approval, as soon as practicable but no later than one year after issuance of a New Project license, a Critically Dry Year Flow Operations and Compliance Plan.  The plan shall establish reasonable procedures and criteria to maintain mean daily water temperatures of 20 degrees Celsius.  These procedures and criteria shall be similar for both increasing flows up to 200 cfs (or any flow between 140 and 200 cfs) and decreasing flows back to 140 cfs.


Table A.3

Rock Creek Reach Minimum River Flow, Pulse, Ramping, & Riparian

Third 5-Year Flow Period - Normal & Wet Years (9)

Season

Month

Base Flow/Cap & Riparian

(cfs) (5)

Pulse (cfs) (6)

Riparian  (10)

Ramping Rate

(cfsD/hr)

Block Loading

Boating Flow (cfs)

Launch Window

Spring

Mar

350/525 & 1000

2 @ >1600

yes

rise & fall from EBF (1)

Belden (3)

-

-

 

Apr

350/525 & 800

2 @ >1600

yes

rise & fall from EBF (1)

Belden (3)

-

-

 

May

350/525 & 600

2 @ >1600

yes

rise & fall from EBF (1)

Belden (3)

-

-

Summer & Fall

Jun

600 to 260/390

1 @ >1000 (2)

yes

300/400 cfs rise 150 cfs fall (4)

Belden (3)

1600

10 - 4 pm

 

Jul

260/390

0

no

400 cfs rise 150 cfs fall

no

1200

10 - 4 pm

 

Aug

260/390

0

no

400 cfs rise

150 cfs fall

no

1000

10 - 4 pm

 

Sep

260/390

0

no

400 cfs rise

150 cfs fall

no

1000

10 - 4 pm

 

Oct

260/390

0

no

400 cfs rise
150 cfs fall

no

1000

10 - 4 pm

 

Nov

260/390

0

no

400 cfs rise

150 cfs fall

no

-

-

Winter

Dec

350/525

0

no

400 cfs rise

150 cfs fall

no

-

-

 

Jan

350/525

0

no

400 cfs rise

150 cfs fall

no

-

-

 

Feb

350/525

0

no

400 cfs rise

150 cfs fall

no

-

-

Notes:

(1)  Rise and fall to follow E. Branch Feather rate, to be achieved by holding Belden and Rock Creek PHs constant during pulse (unless RCPH decreased to maintain flow > target pulse).  Pulse event can be terminated when EBF flow is constant (+-100 cfs/hr), at which time normal operations resume, and spill may be reduced at 150 cfs/hr. Same rise and fall ramping limitations apply to non-pulse spill events past diversion dam during March - first 2 weeks of June.      

(2)  In first 2 weeks of June, a pulse of 1000 cfs (from EBF or supplemented) of at least 12 continuous hours in duration should occur, assuming flows at NF57 are not already in excess of 3000 cfs.      

(3)  If flows at NF57 are between 275 and 3000 cfs, Belden will be block loaded to avoid having spills start and stop at Rock Creek Reservoir.      

(4)  300 cfs/hr rise during first 2 weeks of June, 400 cfs/hr rise for second 2 weeks of June if spill is from operations.      

(5)  Minimum monthly flow to be measured at Licensee gage NF57.      

(6)  Pulses are 12 hrs continuous duration.

(9)  Minimum flows in this table set by the ERC based on monitoring results

(10)  Riparian test flows elevate base flow from March 15-30, 1000 cfs continuous. For April 1-30, 20 of 30 days at 800 cfs, for May 1-31, 20 of 30 days at 600 cfs, base/cap flow otherwise.  From June 1 - 15, ramp in two steps to base/cap.  After the 5-yr test and assoc. monitoring, riparian releases may cease unless significant resource improvement is observed.


Table A.3  (Continued)

 

Rock Creek Reach Minimum River Flow, Pulse, Ramping, & Riparian

Third 5-Year Flow Period - Dry Years (9)

Season

Month

Base Flow/Cap & Riparian (cfs) (5)

Pulse (cfs) (6)

Riparian  (10)

Ramping Rate

(cfsD/hr)

Block Loading

Boating Flow (cfs)

Launch Window

Spring

Mar

280/420 & 800

2 @ >1000

yes

rise & fall from EBF (1)

Belden (3)

-

-

 

Apr

280/420 & 640

2 @ >1000

yes

rise & fall from EBF (1)

Belden (3)

-

-

 

May

280/420 & 480

0

yes

rise & fall from EBF (1)

Belden (3)

-

-

Summer & Fall

Jun

480 to 210/310

0

yes

300/400 cfs rise 150 cfs fall (4)

no

1000

10 - 1 pm

 

Jul

210/310

0

no

400 cfs rise

150 cfs fall

no

800

10 - 1 pm

 

Aug

210/310

0

no

400 cfs rise

150 cfs fall

no

800

10 - 1 pm

 

Sep

210/310

0

no

400 cfs rise

150 cfs fall

no

800

10 - 1 pm

 

Oct

210/310

0

no

400 cfs rise

150 cfs fall

no

-

-

 

Nov

210/310

0

no

400 cfs rise

150 cfs fall

no

-

-

Winter

Dec

280/420

0

no

400 cfs rise

150 cfs fall

no

-

-

 

Jan

280/420

0

no

400 cfs rise

150 cfs fall

no

-

-

 

Feb

280/420

0

no

400 cfs rise

150 cfs fall

no

-

-

Notes:

(1)  Rise and fall to follow E. Branch Feather rate, to be achieved by holding Belden and Rock Creek PHs constant during pulse (unless RCPH decreased to maintain flow > target pulse).  Pulse event can be terminated when EBF flow is constant (+-100 cfs/hr), at which time normal operations resume, and spill may be reduced at 150 cfs/hr. Same rise and fall ramping limitations apply to non-pulse spill events past diversion dam during March - first 2 weeks of June.      

(3)  If flows at NF57 are between 275 and 3000 cfs, Belden will be block loaded to avoid having spills start and stop at Rock Creek Reservoir.      

(4)  300 cfs/hr rise during first 2 weeks of June, 400 cfs/hr rise for second 2 weeks of June if spill is from operations.      

(5)  Minimum monthly flow to be measured at Licensee gage NF57.       

(6)  Pulses are 12 hrs continuous duration.

(9)  Minimum flows in this table set by the ERC based on monitoring results

(10)          Riparian test flows elevate base flow from March 15-30, 800 cfs continuous. For April 1-30, 20 of 30 days at 640 cfs, for May 1-31, 20 of 30 days at 480 cfs, base/cap flow otherwise.  From June 1 - 15, ramp in two steps to base/cap.  Riparian releases occur only in first year of consecutive dry year sequences.  After the 5-yr test and assoc. monitoring, riparian releases may cease unless significant resource improvement is observed.      

 


Table A.3  (Continued)

 

Rock Creek Reach Minimum River Flow, Pulse, Ramping, & Riparian

Third 5-Year Flow Period - Critically Dry Years

Season

Month

Base Flow (cfs) (5)

Pulse (cfs) (6)

Riparian

(6)

Ramping Rate

(cfsD/hr)

Block Loading

Boating Flow (cfs)

Launch Window

Spring

Mar

150

1 @ >1000

no

rise & fall from EBF (1)

Belden (3)

-

-

 

Apr

150

1 @ >1000

no

rise & fall from EBF (1)

Belden (3)

-

-

 

May

150

0

no

rise & fall from EBF (1)

Belden (3)

-

-

Summer & Fall

Jun

150 (7)

0

no

300/400 cfs rise

150 cfs fall (4)

no

1000

10 - 1 pm

 

Jul

150 (7)

0

no

400 cfs rise/150 cfs fall

no

800

10 - 1 pm

 

Aug

150 (7)

0

no

400 cfs rise/150 cfs fall

no

800

10 - 1 pm

 

Sep

150 (7)

0

no

400 cfs rise/150 cfs fall

no

800

10 - 1 pm

 

Oct

150 (7)

0

no

400 cfs rise/150 cfs fall

no

-

-

 

Nov

110

0

no

400 cfs rise/150 cfs fall

no

-

-

Winter

Dec

110

0

no

400 cfs rise/150 cfs fall

no

-

-

 

Jan

110

0

no

400 cfs rise/150 cfs fall

no

-

-

 

Feb

110

0

no

400 cfs rise/150 cfs fall

no

-

-

Notes: 

(1)  Rise and fall to follow E. Branch Feather rate, to be achieved by holding Belden and Rock Creek PHs constant during pulse (unless RCPH decreased to maintain flow > target pulse).  Pulse event can be terminated when EBF flow is constant (+-100 cfs/hr), at which time normal operations resume, and spill may be reduced at 150 cfs/hr       

(3)  If flows at NF57 are between 275 and 3000 cfs, Belden will be block loaded to avoid having spills start and stop at Rock Creek Reservoir.      

(4)  300 cfs/hr rise during first 2 weeks of June, 400 cfs/hr rise for second 2 weeks of June if spill is from operations.      

(5)  Minimum monthly flow to be measured at Licensee gage NF57.   

(6)  Pulses are 12 hrs continuous duration, and no riparian flows occur in critically dry years

(7)  The base flow of 150 cfs shall be increased to 200 cfs, or to any flow between 150 and 200 cfs, to the extent necessary to contribute to the maintenance of mean daily temperatures of 20 degrees Celsius or less in the Rock Creek Reach.  Similarly, this increased flow shall be reduced back to the 150 cfs base flow when not required to maintain mean daily temperatures of 20 degrees Celsius in the Rock Creek Reach.  For the first three years after issuance of a New Project license, or until a temperature model as referred to in Section I, Paragraph 3 is developed, Licensee shall use the mean daily water temperature measured at NF 57 to determine whether and how to implement this flow provision.  This flow provision shall not apply, and the base flow shall remain at 150 cfs, if the ERC and FS determine, based on a review of temperature monitoring results or by assessment from a reasonably accurate water temperature model, that the increase in base flows will not result in a reduction in water temperature beneficial to cold freshwater habitat, or the cost of the increase in base flow is dramatically disproportional to the benefit.  To implement this flow provision, Licensee shall, in consultation with the ERC and FS, submit to FERC for approval, as soon as practicable but no later than one year after issuance of a New Project license, a Critically Dry Year Flow Operations and Compliance Plan.  The plan shall establish reasonable procedures and criteria to support maintenance of mean daily water temperatures of 20 degrees Celsius.  These procedures and criteria shall be similar for both increasing flows up to 200 cfs (or any flow between 150 and 200 cfs) and decreasing flows back to 150 cfs.


Table A.3  (Continued)

 

Cresta Reach Minimum River Flow, Pulse, and Ramping

Third 5-Year Flow Period - Normal & Wet Years (9)

Season

Month

Base Flow/Cap (cfs) (5)

Pulse (cfs) (6)

Ramping Rate

(cfsD/hr)

Block Loading

Boating Flow (cfs)

Launch Window

Spring

Mar

350/525

2 @ >1600

rise & fall from EBF (1)

Belden (3)

-

-

 

Apr

350/525

2 @ >1600

rise & fall from EBF (1)

Belden (3)

-

-

 

May

350/525

2 @ >1600

rise & fall from EBF (1)

Belden (3)

-

-

Summer & Fall

Jun

325/440

1 @ >1000 (2)

300/400 cfs rise

150 cfs fall (4)

Belden (3)

1600

10 - 4 pm

 

Jul

325/440

0

400 cfs rise/150 cfs fall

no

1200

10 - 4 pm

 

Aug

325/440

0

400 cfs rise/150 cfs fall

no

1000

10 - 4 pm

 

Sep

325/440

0

400 cfs rise/150 cfs fall

no

1000

10 - 4 pm

 

Oct

325/440

0

400 cfs rise/150 cfs fall

no

1000

10 - 4 pm

 

Nov

325/440

0

400 cfs rise/150 cfs fall

no

-

-

Winter

Dec

350/525

0

400 cfs rise/150 cfs fall

no

-

-

 

Jan

350/525

0

400 cfs rise/150 cfs fall

no

-

-

 

Feb

350/525

0

400 cfs rise/150 cfs fall

no

-

-

Notes:,

(1)  Rise and fall to follow E. Branch Feather rate, to be achieved by holding Belden, Rock Creek, & Cresta PHs constant during pulse (unless Cresta PH decreased to maintain flow > target pulse).  Pulse event can be terminated when EBF flow is constant (+/-100 cfs/hr), at which time normal operations resume, and spill may be reduced at 150 cfs/hr. Same rise and fall ramping limitations apply to non-pulse spill events past diversion dam during March - first 2 weeks of June.     

(2)  In first 2 weeks of June, a pulse of 1000 cfs (from EBF or supplemented) of at least 12 continuous hours in duration should occur, assuming flows at NF56 are not already > 3000 cfs.     

(3)  If flows at NF56 are between 275 and 3000 cfs, Belden & Rock Creek will be block loaded to avoid having spills start and stop at Cresta Reservoir.     

(4)  300 cfs/hr rise during first 2 weeks of June, 400 cfs/hr rise for second 2 weeks of June if spill is operations.     

(5)  Minimum monthly flow to be measured at Licensee gage NF56, and at least 100 cfs will be released from Cresta Diversion Dam at all times.      

(6)  Pulses are 12 hrs continuous duration, and no riparian flows occur.

(9)  Minimum flows in this table set by the ERC based on monitoring results.


Table A.3  (Continued)

 

Cresta Reach Minimum River Flow, Pulse, and Ramping

Third 5-Year Flow Period - Dry Years (9)

Season

Month

Base Flow/Cap (cfs) (5)

Pulse (cfs) (6)

Ramping Rate

(cfsD/hr)

Block Loading

Boating Flow (cfs)

Launch Window

Spring

Mar

280/420

2 @ >1000

rise & fall from EBF (1)

Belden (3)

-

-

 

Apr

280/420

2 @ >1000

rise & fall from EBF (1)

Belden (3)

-

-

 

May

280/420

0

rise & fall from EBF (1)

Belden (3)

-

-

Summer & Fall

Jun

260/350

0

300/400 cfs rise/150 cfs fall (4)

no

1000

10 - 1 pm

 

Jul

260/350

0

400 cfs rise/150 cfs fall

no

800

10 - 1 pm

 

Aug

260/350

0

400 cfs rise/150 cfs fall

no

800

10 - 1 pm

 

Sep

260/350

0

400 cfs rise/150 cfs fall

no

800

10 - 1 pm

 

Oct

260/350

0

400 cfs rise/150 cfs fall

no

-

-

 

Nov

260/350

0

400 cfs rise/150 cfs fall

no

-

-

Winter

Dec

280/420

0

400 cfs rise/150 cfs fall

no

-

-

 

Jan

280/420

0

400 cfs rise/150 cfs fall

no

-

-

 

Feb

280/420

0

400 cfs rise/150 cfs fall

no

-

-

Notes:

(1)  Rise and fall to follow E. Branch Feather rate, to be achieved by holding Belden, Rock Creek, & Cresta PHs constant during pulse (unless Cresta PH decreased to maintain flow > target pulse).  Pulse event can be terminated when EBF flow is constant (+/-100 cfs/hr), at which time normal operations resume, and spill may be reduced at 150 cfs/hr. Same rise and fall ramping limitations apply to non-pulse spill events past diversion dam during March - first 2 weeks of June.     

(3)  If flows at NF56 are between 225 and 3000 cfs, Belden & Cresta will be block loaded to avoid having spills start and stop at Cresta Reservoir.     

(4)  300 cfs/hr rise during first 2 weeks of June, 400 cfs/hr rise for second 2 weeks of June if spill is from operations.     

(5)  Minimum monthly flow to be measured at Licensee gage NF56, and at least 100 cfs will be released from Cresta Diversion Dam at all times.      

(6)  Pulses are 12 hrs continuous duration, and no riparian flows occur.

(9)  Minimum flows in this table set by the ERC based on monitoring results.


Table A.3  (Continued)

 

Cresta Reach Minimum River Flow, Pulse, and Ramping

Third 5-Year Flow Period - Critically Dry Years

Season

Month

Base Flow  (CFS) (5)

Pulse (cfs) (6)

Ramping Rate

(cfsD/hr)

Block Loading

Boating Flow (cfs)

Launch Window

Spring

Mar

100

1 @ >1000

rise & fall from EBF (1)

Belden (3)

-

-

 

Apr

100

1 @ >1000

rise & fall from EBF (1)

Belden (3)

-

-

 

May

140

0

rise & fall from EBF (1)

Belden (3)

-

-

Summer

& Fall

Jun

140 (7)

0

300/400 cfs rise

150 cfs fall (4)

no

1000

10 - 1 pm

 

Jul

140 (7)

0

400 cfs rise/150 cfs fall

no

800

10 - 1 pm

 

Aug

140 (7)

0

400 cfs rise/150 cfs fall

no

800

10 - 1 pm

 

Sep

140 (7)

0

400 cfs rise/150 cfs fall

no

800

10 - 1 pm

 

Oct

140 (7)

0

400 cfs rise/150 cfs fall

no

-

-

 

Nov

100

0

400 cfs rise/150 cfs fall

no

-

-

Winter

Dec

100

0

400 cfs rise/150 cfs fall

no

-

-

 

Jan

100

0

400 cfs rise/150 cfs fall

no

-

-

 

Feb

100

0

400 cfs rise/150 cfs fall

no

-

-

Notes: 

(1)  Rise and fall to follow E. Branch Feather rate, to be achieved by holding Belden, Rock Creek, Cresta PHs constant during pulse (unless Cresta PH decreased to maintain flow > target pulse).  Pulse event can be terminated when EBF flow is constant (+-100 cfs/hr), at which time normal operations resume, and spill may be reduced at 150 cfs/hr.      

(3)  f flows at NF56 are between 225 and 3000 cfs, Belden & Cresta will be block loaded to avoid having spills start and stop at Cresta Reservoir.     

(4)  300 cfs/hr rise during first 2 weeks of June, 400 cfs/hr rise for second 2 weeks of June if spill is from operations.     

(5)  Minimum monthly flow to be measured at Licensee gage NF56, and at least 100 cfs will be released from Cresta Diversion Dam at all times.      

(6)  Pulses are 12 hrs continuous duration, and no riparian flows occur.

(7)  The base flow of 140 cfs shall be increased to 200 cfs, or to any flow in between 140 and 200 cfs, to the extent necessary to contribute to the maintenance of mean daily temperatures of 20 degrees Celsius or less in the Cresta Reach.  Similarly, this increased flow shall be reduced back to the 140 cfs base flow when not required to maintain mean daily temperatures of 20 degrees Celsius in the Cresta Reach.  For the first three years after issuance of a New Project license, or until a temperature model as referred to in Section I, Paragraph 3 is developed, Licensee shall use the mean daily water temperature measured at NF 56 to determine whether and how to implement this provision.   This flow provision shall not apply, and the base flow shall remain at 140 cfs, if the ERC and FS determine, based on a review of temperature monitoring results or by assessment from a reasonably accurate water temperature model, that the increase in base flows will not result in a reduction in water temperature beneficial to cold freshwater habitat, or the cost of the increase in base flow is dramatically disproportional to the benefit.  To implement this flow provision, Licensee shall, in consultation with the ERC and FS, submit to FERC for approval, as soon as practicable but no later than one year after issuance of a New Project license, a Critically Dry Year Flow Operations and Compliance Plan.  The plan shall establish reasonable procedures and criteria to maintain mean daily water temperatures of 20 degrees Celsius.  These procedures and criteria shall be similar for both increasing flows up to 200 cfs (or any flow between 140 and 200 cfs) and decreasing flows back to 140 cfs.


 


 

 

2.  Water Year TypeMinimum streamflows vary depending on the magnitude of the annual runoff from the river basin.  Water years have been separated into four water year types based on the California Department of Water Resources (DWR) records of annual inflow to Lake Oroville (Oroville) from 1930-1999:  Wet, Normal, Dry, and Critically Dry (CD).  Licensee shall determine water year type based on the predicted unimpaired inflow to Oroville and spring snowmelt runoff forecasts provided by Licensee and DWR each month from March through May.  The water year types are defined as follows:

 

Wet:            Greater than or equal to 5,679 thousand acre feet (TAF) inflow to Oroville

Normal:       Less than 5,679 TAF but greater than or equal to 3,228 TAF inflow to Oroville

Dry:             Less than 3,228 TAF but greater than or equal to 2,505 TAF inflow to Oroville

CD:              Less than 2,505 TAF inflow to Oroville

 

Licensee shall make a forecast of the water year type on or about March 10 and operate for the remainder of that month and until the next forecast based on that March forecast.  New forecasts will be made on or about the tenth of April and May after the snow surveys are completed and operations will be changed as may be appropriate.  The May forecast shall be used to establish the water year type for the remaining months of the year until the next March, when forecasting shall begin again.  Licensee shall provide Notice to FS, FERC, and the ERC of the final water year type determination within 30 days of making the determination.

 

3.  River Flow Measurement.  For the purpose of determining the river stage and Minimum River Flow below the Rock Creek and Cresta dams, Licensee shall use, operate and maintain the existing gage locations (designated as USGS gage numbers 11.4032.00 and 11.4043.30) consistent with all requirements of the USGS and FERC.  The minimum 100 cfs release at Cresta Dam will be verified by records from flow meters on release facilities at the dams or by records of radial gates operations.

 

4.  Initial Year Flow Variation Allowance.  Licensee shall have a one year interim test procedure that will allow variations in flow releases of up to 10% below the minimum flows specified in Table A.1 and of a duration no longer than 24 hours, provided that Licensee targets flows above the specified level to help minimize the frequency of any under-releases and Licensee compensates for each under-release by providing over-releases of sufficient flow and duration to equal the cumulative volume of the under-release within sixty days. 

 

5.  Ramping Rates.  For the preservation and improvement of aquatic resources in the Project area, Licensee shall control river flows during controllable periods by ramping as follows:


A.  Basic Ramping Rates.  During periods when ramping can be controlled, the following will be the initial Ramping Rates during the first three years after acceptance of the new license.  These rates will be followed as close as reasonably practicable given radial gate operating limitations.  Revision to these rates may occur as the result of the monitoring plan as provided under item F below.  Water to accommodate future adjustments to Ramping Rates as applied to controlled Pulse Flow releases shall be made up from the total volume of water for such Pulse Flows, or Minimum River Flows.

 

March, April and May - 250 cfs/hr. up-ramp and 150 cfs/hr. down-ramp

June 1 - June 15        -   300 cfs/hr. up-ramp and 150 cfs/hr. down-ramp

Remainder of the year - 400 cfs/hr. up-ramp and 150 cfs/hr. down-ramp

 

B.  Uncontrolled Spill Flows below 3000 cfs. Except during emergencies, up-Ramping Rates will, within limits as discussed herein, match the rise occurring in the East Branch of the North Fork Feather River at the time that the flow capacity of the generating units is exceeded.  Physical limitations of existing gates and controls, dam safety considerations, and other limitations may prevent an exact match of rates.  Down-ramping will be at the rate of fall of the East Branch of the North Fork Feather River provided that as the flow approaches the point that spill can be eliminated, Licensee will make a Good Faith effort to not exceed the basic down-ramp rate specified in Section 5.A above when increasing powerhouse flow.  During Pulse Flow events as defined in the flow schedule, Licensee may hold the generating unit(s) constant below maximum capacity or reduce the generation to produce the required Pulse Flow.  The up-Ramping Rate resulting from reduction in generation plus the observed rise in the East Branch of the North Fork Feather River shall not exceed the basic Ramping Rates under Section 5.A above.  Pulse events can be terminated when East Branch flow is constant (flow rate is not fluctuating more than +/- 100 cfs/hr.) at which time normal operations resume and spill may be reduced at the basic down-ramp rate.

 

C.  Uncontrolled Spills above 3000 cfs.  Radial gates operate to release spills up to approximately 3000 cfs at which time the drum gates typically begin operation.  Drum gate operation can not be as closely controlled as radial gate operation and the potential impacts to the downstream ecological system due to the Ramping Rate are substantially less than at lower flow levels.  Therefore, no Ramping Rate will be imposed for operation above 3000 cfs.

 

D.  Controlled Spills.  If spills are necessary for efficient operation, such as the bypassing of water around a powerhouse to allow its use at upstream or downstream powerhouses, or for special releases such as Pulse Flows required under the Flow Schedule at times when natural flows are not available and for whitewater flows, the ramping shall follow the basic Ramping Rate.

 


E.  Emergencies.  Licensee shall make a Good Faith effort to control Ramping Rates within the parameters provided in this Settlement but shall not be in violation of the rates in the event that the rates are exceeded due to a unit tripping off-line, and subsequent restoration, or other conditions beyond the reasonable control of Licensee.

 

F.  Ramping Study.  The potential affects associated with Ramping Rates will be evaluated in connection with recreation and Pulse Flow releases, as described in Section V.2 of this agreement.  This study shall include a minimum testing period of three years.  If during this period the ERC and FS determine that changes are needed to the initial level of the basic Ramping Rates, Licensee will submit to the FERC revised Ramping Rates as soon as practicable.

 

6.  Annual Ramping Data Review.  As part of the annual data provided to the ERC and FS by January 15 of each year, Licensee shall provide information on its operations during the previous calendar year including Ramping Rates experienced at Rock Creek and Cresta Dams at times that spill occurred.

 

7.  Fishery Monitoring Plan.  To evaluate fish populations and angler use/catch at Rock Creek-Cresta, Licensee shall prepare a Fishery Monitoring Plan, in consultation with the ERC, and FS, and file such plan with FERC as soon as practicable but not more than one year after issuance of the New Project License.  Unless otherwise agreed by the ERC and FS, stocking of fish in the reservoir or river reaches will not be implemented.  Also, due to the low probability of entrainment of trout in the Project intakes, entrainment studies will not be required.

 

8.  Riparian Monitoring Plan.  To evaluate the riparian response to the flow regime in Table A, Licensee shall prepare a Riparian Monitoring Plan, in consultation with the ERC and FS, and file such plan with FERCwithin one year of issuance of a New Project License.

 

9.  Macroinvertebrate Sampling Plan.  To assess possible changes in macroinvertebrate assemblage in response to watershed management actions including changes to instream flow and temperature, Licensee shall develop a Macroinvertebrate Sampling Plan in consultation with the ERC and FS, and file such plan with FERC within one year of issuance of a New Project License.

 

Section III. Habitat Improvements

 

1.  Fishery Habitat Improvements.  To provide improved trout production through instream enhancement of passage, spawning and recruitment, Licensee shall complete the following items A and B within one year and items C and D within 2 years of issuance of a New Project License.

 

 

A.  Provide appropriate size spawning gravel to cover an area of approximately 75 square feet at Granite Creek, tributary to the North Fork Feather River, and maintain this spawning gravel site on an as-needed basis as determined by the ERC.

 

B.  Mechanically remove portions of the existing weir located 100 feet upstream of the mouth of Rock Creek at Cresta Reservoir and downstream of the Union Pacific Railroad bridge crossing Rock Creek, tributary to the North Fork Feather River.

 

C.  Construct, operate, and maintain a spawning channel at Opapee Creek, tributary to the North Fork Feather River.  The design of the spawning channel will be similar to that described in the March 31, 1987, Bechtel Construction, Inc. report entitled “Tributary Improvement Feasibility Study for Selected Streams in the North Fork Feather River Drainage.”

 

D.  Construct, operate, and maintain a spawning channel at Milk Ranch Creek, tributary to the North Fork Feather River.  The design of the spawning channel will be similar to that described in the March 31, 1987, Bechtel Construction, Inc. report entitled “Tributary Improvement Feasibility Study for Selected Streams in the North Fork Feather River Drainage.”

2.  Fishery Habitat Monitoring Plan.  To evaluate the success of spawning channels at Opapee and Milk Ranch Creeks and fish passage at selected tributaries, Licensee shall prepare a Fishery Habitat Monitoring Plan, in consultation with the ERC and FS, and file such plan with FERC within one year of issuance of a New Project License. 

3.  River Terrace Plantings.  To enhance habitat conditions on the upper banks of the NFFR in the Project area, Licensee shall prepare a Terrace Planting Plan, in consultation with the ERC and FS, and file such plan with FERCwithin one year of issuance of a New Project License.  Planting sites will include Rogers Flat, lower Opapee Flat, Chambers Creek, the lower end of Shady Rest and two other sites to be determined for a total of six sites. 

4.  Terrace Planting Monitoring Plan.  Licensee shall also prepare, in consultation with the ERC and FS, a Terrace Planting Monitoring Plan and file such plan with FERC within one year of issuance of a New Project License.  This plan shall determine survival, vigor and canopy development of riparian species established at planting sites and maintained through accepted horticultural techniques.

 

Section IV. River Sediment Management

 

1.  Drum and Radial Gate Operating Plan.  For the purposes of improving sediment recruitment through the Rock Creek and Cresta reaches, Licensee shall, to the extent feasible,  develop a Drum and Radial Gate Operation Plan that would promote bedload movement through the Rock Creek and Cresta reservoirs between December 1 and March 30.  Licensee shall prepare this plan in consultation with the ERC and FS, and file the plan with FERC within one year of issuance of a New Project License.  The plan will include an evaluation of risk of damage to the gates, release pipes, powerhouse intakes, or other facilities. 

 

2.  River Sediment Management Monitoring Plan.  Licensee shall also develop, in consultation with the ERC and FS, a River Sediment Management Monitoring Plan to evaluate the effectiveness of the Gate Operation Plan over a five year test period and file that plan with FERC within one year of issuance of a New Project License.  Releases of water from the drum and radial gates for the purposes of the test program shall be from December 1 to March 30.  The test shall be for a  period of 5 normal or wet years.  At the end of five year test period, the ERC and FS shall evaluate the results of the sediment management program and recommend to FERC future sediment management actions.  If the test program is determined to be successful by the ERC and FS, it shall be implemented for the life of the New Project License.

 

If the ERC determines the test program to be unsuccessful, Licensee shall, within one year of this determination, develop a plan for experimental gravel placement in consultation with the ERC and  FS.  This experimental program will evaluate placement of a quantity of gravel not to exceed 200 cubic yards.  If the ERC determines this program to be successful, then a program of gravel addition not to exceed 100 cubic yards annually shall be implemented for the life of the New Project License.

Section V. Recreation Flow Management  

 

1.  Recreational Flows.  For the purposes of improving and enhancing public recreation, Licensee shall implement, as early as possible but no later than one year after issuance of the New Project License, the following recreational flow schedule and other provisions presented in Table B, Recreation Flow Schedule.

 

A.  Recreation Flow Schedule  Flow releases will occur at both the Rock Creek and Cresta dams according to the schedule below.  Flow releases will occur on Saturdays or Sundays between the hours of 10am and 4pm during wet or normal water years, and between the hours of 10am and 1pm during dry years.  When scheduling flow releases, holiday weekends will be given priority over non-holiday weekends.


 

Table B - Recreation Flow Schedule

 

Month Release amount in Cubic Feet per Second (cfs)

Release Days per Month

 

User Day Triggers

 

  Dry *

Normal

**

Dry

Start

Dry

Cap

Normal

Start

Normal

Cap

Rock Creek

Reach

Cresta Reach
             

Normal /Dry

   Up

Down

Normal /Dry

   Up

Down
June 1000cfs 1600 cfs 1 day

4 days

1 day 5 days 120/110 60 60/50 40
July 800 cfs 1200 cfs 1 day 4 days 1 day 4 days 130/130 60 60/65 40
Aug 800 cfs 1000 cfs 1 day 4 days 1 day 4 days 150/160 60 80/80 50
Sep 800 cfs 1000 cfs 1 day 4 days 1 day 4 days 180/190 80 100/95 60
Oct 800 cfs 1000 cfs 0 0 1 day 2 days 180 80 100 60

 

*    Dry and Critically Dry years

**  Normal and Wet years

 

B.  Recreation Flow Calendar.  An annual recreation flow calendar will be established  with initial recreation flow days occurring on the first full weekend of the month.  If Licensee is required to make a June Pulse Flow release, such release shall be scheduled coincident with a June recreation flow day(s).  An annual planning meeting will be held each year in March.  This meeting will discuss expected water year type, results of monitoring efforts, Licensee maintenance needs that may conflict with recreation flow releases, and other issues relevant to on-water recreation.

 

C.  Flows Made on Consecutive Days.  Recreation flow releases from Rock Creek and Cresta dams will be made on consecutive days.  Increases or decreases in the number of recreation flow releases as a result of monitoring will be made to the recreation flow calendar on weekends starting with the second weekend of the month.  If there is an odd number of recreation flow releases due to additional days, then the odd recreation flow release will occur on the first weekend day following the consecutive weekend day recreation flow release.

 

D.  Recreation Flow Postponement.  Licensee may postpone up to one weekend of recreation flow releases in July and one weekend of recreation flow releases in August during heat waves provided Licensee gives a 48-hour notice to the recreation community.  Postponement will be based on projected Heat Storm conditions.  Postponed recreation flow releases will be made up on the next available weekend in the same month or rolled into the following month if no weekends are available. Also in the event of an emergency which would preclude the release of a scheduled flow, Licensee shall provide as much notice as possible and arrangements for the rescheduled day or days.

 

E.  Triggers for Adjustments.  Observed boater use in boater days will be monitored to determine whether release days should be added or subtracted.  A boater day is defined as use of either the Rock Creek or Cresta reaches for any part of a given day.  Boater use data will be collected on each scheduled recreation flow release days.  A day of recreation flow will be added to the recreation flow schedule the next year after 100% exceedance of the up-trigger is met for each day in a particular month of that year.  A day of recreation flow will be subtracted from the recreation flow schedule for the next year after 100% exceedance of the down-trigger are not met in a particular month of that year.  Days will be adjusted to the same month in which use is monitored.  Recreation flow releases will not decrease below 1 release per month, unless unacceptable adverse ecological impacts are observed.  Flow release days will not be added or subtracted during the initial 3 years after issuance of the license to allow for the biologic monitoring in item (V.2) below.

 

F.  Ramping Rates.  Initial Ramping Rates will be as defined in the Section II.5.A .  Subsequent ramp rate adjustments made by the ERC and FS, and approved by FERC if necessary, will come out of the total volume of water released during the recreation flow release, except in dry years, provided that Licensee shall not be required to provide additional flow if the ramping time for dry years increases by more than a factor of 2.

 

2.  Recreation and Pulse Flow Biological Evaluation.  Licensee shall prepare, in consultation with the ERC and FS, a Flow Evaluation Plan and file such plan  with FERC within one year of issuance of a New Project License.   This Plan will be designed to evaluate the effects of recreation and Pulse Flow releases on aquatic biota, and the metrics to be used in this determination.  If, after 3 years of data collection and assessment, either beneficial, neutral, or no significant adverse effects (as determined by the ERC and FS) are observed, recreation flow release days will be added as supported by on-water recreational use monitoring in item V.1.E above.  Days will be adjusted after that period as supported by ecological and on-water recreational use monitoring

3.  Recreation Stream Flow Information.  Each year Licensee shall make recreation stream flow information available to the public via toll-free phone and/or Internet.  Summer streamflow release schedules and streamflows below the diversion dams shall be provided during various periods and in various formats, as described below. 

A.  By April 10, a preliminary forecast shall be made of the dates and flow targets of scheduled recreational releases from the Rock Creek and Cresta Diversion Dams.  The forecast shall be updated by May 10, with weekly updates if changes occur, thereafter through October 15.

 

B.  To allow whitewater recreational users to take advantage of streamflows that result from snowmelt or storms, hourly averages of streamflows at the Rock Creek and Cresta reach gages (Licensee gages NF57 and NF56, respectively) shall, within 4 hours of collection, be posted on the Internet site for the current and prior 6 days for the entire year.  All streamflow values shall be rounded to the nearest even hundreds value, be in cfs, and plots or tables showing these data will be labeled “These provisional data have not been reviewed or edited and may be subject to significant change.”  The Licensee may, at their discretion but limited by their Good Faith intent to routinely and continuously provide this flow information, block the posting of this information when the information is determined by the Licensee to have significant market value that could adversely affect Licensee bidding activities and power or ancillary services prices. 

 

C.  Licensee shall install and maintain one simple staff gage/depth indicator in both the Rock Creek and Cresta reaches and provide a rough rating table to be posted at the nearby recreational/launch area that reasonably correlates the gage height with flow measured in cubic feet per second (cfs).  Rating tables shall be updated as needed, no more often than annually.   Licensee will make a Good Faith attempt to locate the staff gages/ depth indicators in locations that are easily accessible for public reference.

 

Licensee shall make a Good Faith effort to make scheduled recreation streamflow releases on the days when such releases are forecast to occur.  The Licensee has the discretion to cancel scheduled releases up to 48 hours prior to the release during Heat Storm conditions (see Section V.1.D, Recreation Flow Postponement).  All provisions for recreation streamflows are subject to the safe operability of the Project facilities and equipment necessary to provide such streamflows.  Licensee shall make a Good Faith effort to maintain the operability of such Project facilities and equipment and shall not schedule discretionary outages of such Project facilities and equipment in conflict with providing the recreation streamflows described below.  The flow information may be made available to the public via a third party.  The flow information protocols described above may be modified upon mutual agreement of Licensee, FS, AW, and acceptance by FERC.

 

Section VI.  River Recreation Facilities

 

1.  River Recreation Access Plan.  Within eighteen (18) months of the date of issuance of the New Project License and for the purposes of enhancing public access, Licensee shall develop in consultation with the ERC and FS, a River Access Management Plan, and file such plan with FERC.  In developing the plan, Licensee shall consider the following (prioritized in order of importance):

·       vehicle access to the bench directly downstream of Rock Creek Dam;

·       public access downstream of Cresta Dam;

·       public access to Licensee lands directly downstream of Cresta powerhouse (old Licensee employee housing site); and

·       public access at the confluence of the NFFR with Rock Creek at the upper end of Cresta Reservoir.

 

The plan will also include an implementation and funding schedule.  Licensee will match funds contributed for recreational access enhancements at these sites up to a cap of $300,000.  $100,000 shall be provided without matching funding and $200,000 shall be subject to matching funding from other sources.  These funds will be escalated as specified in Paragraph 4.5.5 of this Settlement.

 

Licensee shall prepare the plan and schedule in consultation with FS, FWS, CALTRANS, Plumas and Butte Counties, AW, and other appropriate parties.  Licensee shall include with the plan documentation of consultation, copies of comments and recommendations on the completed plan after it has been prepared and provided to the entities, and specific descriptions of how the entities comments are accommodated by the plan.  Licensee shall allow a minimum of 30 days for the entities to comment and to make recommendations prior to filing the plan with FERC for approval.  If Licensee does not adopt a recommendation, the filing shall include Licensee’s reasons, based on Project-specific information.

 

2.  Shady Rest.  Licensee shall continue to operate and maintain the rest area located at Shady Rest.  This site shall also include appropriate river use and natural history interpretive measures and other information appropriate for river use.

 

Section VII.  Public Recreation Monitoring

 

Licensee shall prepare, in consultation with the ERC and FS, a Recreation Monitoring Plan and file such plan with FERC within one year of issuance of a New Project License.  This plan will monitor recreational use during recreation flow release events and monitor fishing recreation through a creel census program.  Licensee shall also cooperate with the FS should FS wish to perform other recreational surveys in the Project area.

 

Section VIII.  Ecological Resources Committee

 

Licensee shall, within 3 months of issuance of a New Project License, in coordination with the Parties, establish the ERC for the purpose of assisting Licensee in the design of monitoring plans, review and evaluation of data, and preparation of adaptive management measures for implementation by Licensee as provided in this Settlement.  Licensee shall provide to FERC, FS, and the ERC by May 31 of each year an annual report of the activities of the ERC.  Licensee shall provide Notice to FERC within 30 days (but prior to implementing the change) of any decisions by the ERC or FS that result in changes to Project operations or facilities.

 

Appendix B

 

 

Protection, Mitigation and Enhancement Measures that the Parties agree are appropriate and necessary, and made a part of the Agreement, but are not recommended to be Included in New Project License and FS Final 4(e) Conditions.

 

Section I.  Objectives

 

The following objectives are desirable outcomes.  It is recognized that factors beyond Licensee’s control could affect attainment of these objectives as determined by the ERC and FS, and that some or all of the objectives may not be achievable within the PM&E measures included in Appendix A of this Settlement.  Licensee agrees to work toward achievement of these objectives by implementing the terms of this Settlement.  The objectives were developed by the Rock Creek - Cresta Relicensing Collaborative as the basis for measures to become Section 4(e) Conditions and license articles.  Fishery performance desired outcomes may be revised during the 15 year study based on site specific analyses of limiting factors, production potential or other biological considerations by the ERC.  These objectives are intended to provide guidance for future activities of the ERC and FS, and are subject to review and amendment or modification as scientific based data are obtained from monitoring and other sources.  If, after review and analysis of the data, the ERC determines that after exhausting the adaptive management measures included in this Settlement the objectives are not achieved, further actions by Licensee are not required absent reopener or license amendment.

 

Water Temperature Objective

 

In order to reasonably protect cold freshwater habitat, maintain mean daily water temperatures of 20°C or less in the Rock Creek and Cresta Reaches up to the funding and flow limits in Appendix A.

 

PM&E Measures that Address this Objective:  The Parties believe that the PM&E measures set forth in Appendix A, Section I, Paragraph 1 will assist in achieving this objective. 

 

Fishery Objective

 

Achieve a desired goal of an excellent trout fishery and functioning ecosystem to all naturally occurring species.  According to the best available information on conditions prior to the Project, fishery performance criteria will include:

 

      a.  Wild rainbow trout population with 4 age classes.

b.  Fish catch 80% wild trout/ 20% non-game fish.

c.  Average wild trout caught > 9.7 inches fork length.

d.  Adult rainbow trout available for catch > 17 inches.

e.  Harvestable component of 595 lbs/mile wild trout.

f.  Wild trout biomass 62 lbs/acre (catch).

g.  Angler catch rate of one fish per angling hour including catch and release.

 

      PM&E Measures that Address this Objective:  The Parties believe that the following actions described in this Settlement will serve to accomplish the goal, and the desired fishery performance outcomes:

 

a.   Flow management through Minimum River Flows, operations and Ramping Rates.

b.   Spawning, passage and recruitment improvements.

c.  Water temperature management.

d.   Sediment/habitat/gravel improvement.

e.   Fisheries management through California Fish and Game Commission adoption of catch-and-release or other conservation oriented sportfishing regulations.

f.  Annual standing crop surveys using creel, snorkel and electrofishing methods.

g.   Measurement of downstream juvenile recruitment.

h.   Monitoring tributaries and spawning channels for fish passage.

i.  Hydro project flow fluctuation ramping studies and impacts.

j.  Habitat and sediment evaluation.

k.  Water temperature monitoring.

l.  Macroinvertebrate surveys

m.  Riparian assessment

n.  Evaluate and report annually the above monitoring actions and provide annual reports comparing new information with past results and progress towards the fishery performance desired outcomes.

 

Macroinvertebrate Objective

Macroinvertebrate indices (metrics) in Project reaches should be comparable to reference reaches located within and outside the NFFR drainage.  The ERC and FS, for areas within its jurisdiction, will develop numerical objectives based on the collection and review of additional macroinvertebrate data.

PM&E Measures that Address this Objective:  The Parties anticipate that the initial ecological requirements that move closer to mimicking the natural hydrograph will work toward achieving this objective.  The Parties further believe that the additional Minimum River Flows listed in Table A of Appendix A and river sediment management adopted under this Settlement will further aid in achieving this objective.

 

Natural Hydrograph Objective

Provide a hydrologic regime that approaches the natural annual hydrograph.

PM&E Measures that Address this Objective:  The Parties believe that this objective is addressed by the Minimum River Flows, Pulse Flow, and Ramping Rate requirements in Appendix A of this Settlement.   The Parties believe that Appendix A of this Settlement provides a framework to evaluate the appropriate magnitude, timing and duration of streamflow necessary to promote a favorable biotic response.

 

Flow Fluctuations Objective

Minimize Project-caused flow fluctuations uncharacteristic of the natural hydrograph to protect biota and maintain public safety.

PM&E Measures that Address this Objective:  The Parties believe that this objective is addressed by the Minimum River Flows, Pulse Flow, Block Loading, Ramping Rate requirements, and other potential mitigative measures in Appendix A of this Settlement.

 

Geomorphology Objective

 

Maintain fluvial processes to provide for balanced sediment transport, channel bed material mobilization and distribution, and channel structural stability distribution that contribute to diverse aquatic habitat and healthy riparian habitat.

 

PM&E Measures that Address this Objective:  The Parties anticipate that the implementation of Minimum River Flows, Pulse Flow and river sediment management provisions included in Appendix A of this Settlement will work toward meeting this objective. 

 

Riparian Habitat Objective

 

Maintain a functioning ecosystem for riparian resources.

 

PM&E Measures that Address this Objective:  The Parties anticipate that the ecological requirements that move closer to mimicking the natural hydrograph will work toward achieving this objective.  The Parties believe that stream ecological monitoring included in Appendix B as well as Minimum River Flows and Terrace Plantings under Appendix A will further aid in achieving this objective.

 

 

Threatened, Endangered, and Sensitive Species Objective

Ensure that PM&E measures developed by the Collaborative and ERC are consistent with any FS biological evaluation for sensitive species or any biological opinion issued under the federal or state Endangered Species Act.

 

PM&E Measures that Address this Objective:  The Parties anticipate that the ecological requirements included in Appendix A of this Settlement and the flow fluctuation study efforts will assist in meeting this objective. 

 

Hydropower Operations Objective

 

Ensure that the Project continues to be a competitive source of least cost, reliable, and flexible hydroelectric power generation.

 

PM&E Measures that Address this Objective:  This objective has been considered in all of the PM&E measures in Appendix A.

 

Recreation Streamflow Objective

 

Provide recreation streamflows that address a spectrum of opportunities, avoid significant ecological impacts, minimize user and ecological conflicts, are consistent with hydropower operations, and maintain a high degree of user satisfaction, as determined by user surveys.

 

PM&E Measures that Address this Objective:  The Parties believe that the recreation streamflows specified in Appendix A address this objective.  The specified ecological and recreational boating monitoring will assist in determining if this objective is being met.

 

Recreational Access Objective

 

Provide river recreation facilities that are consistent with Recreation Opportunity Spectrum (ROS) class (or equivalent), physical, social, and ecological carrying capacity of the resource and demand levels, with the possibility of adjustment based on user satisfaction.

 

PM&E Measures that Address this Objective:  The Parties believe that the potential whitewater boating access facilities specified in Appendix A address this objective.

 


Streamflow Information Objective

 

Provide streamflow information for Project-affected whitewater runs that is available to the general public and is adequate for river recreation use while protecting Licensee’s proprietary information.

 

PM&E Measures that Address this Objective:  The Parties believe that the streamflow information measures specified in Appendix A will achieve this objective.

 

Resource Protection Objective

 

Ensure that recreation and Pulse Flows do not adversely affect other resources.

 

PM&E Measures that Address this Objective:  The Parties believe that the Recreation and Pulse Flow Biological Evaluation will assist in avoiding impacts on sensitive amphibians and other sensitive resources.

 

Section II.  Ecological Resources Committee (ERC)

 

Purpose:  The primary purpose of this committee will be to assist Licensee in design of the monitoring plans, review and evaluation of data, and making specific decisions regarding ecological resources and flow related issues to be addressed by Licensee as provided in this Settlement.

Members:  The membership of the ERC shall consist only of representatives of the Original Parties to this Settlement except FS, which will designate a liaison(s) to the ERC. The ERC may add to its membership by unanimous agreement not subject to dispute resolution.

 

Establishment: Licensee shall establish the ERC within 3 months of issuance of a New Project License.  Licensee shall establish the ERC on an interim basis within 1 month after the Effective Date of this Settlement for the limited purpose of assisting Licensee in actions specified in this Settlement and scheduled for implementation in advance of issuance of the New Project License.

 

Meetings:  Licensee shall hold an Annual Meeting of the ERC prior to April 30 of each year to discuss the results of the previous year’s monitoring, actions to be taken and information to be submitted to the FERC.  Additional meetings may occur as the Committee deems necessary.

 

Conduct of Meetings:  Licensee shall be responsible for chairing each meeting and providing timely meeting notes.  Licensee shall arrange meeting times and places that are acceptable to as many ERC members as possible.

 

Meeting Notices:  The Annual Meeting will be Noticed to all ERC members and FS, and representatives of all ERC members and FS may attend.  Meetings other than the Annual Meeting may be held on Notice of no less than 7 days.  The ERC shall adopt procedures for reasonable public participation consistent with applicable law.

 

Responsibility of the ERC:

·       Work cooperatively with Licensee to develop and implement monitoring programs as described in Appendices A and B of this Settlement. 

·       Meet at least annually to review data and effectiveness of the monitoring effort.

·       Analyze monitoring results including:
1)      An evaluation and report of existing information created during the past license operations for use in comparison to future monitoring results.

2)    An evaluation and report of monitoring during the first five year period of increased instream flows and comparison to item 1)

3)    An evaluation and report of monitoring during the second five year period of increased instream flows and comparison to item 1) and 2).

4)    An evaluation and report of monitoring during the third five year period of increased instream flows and comparison to item 1), 2) and 3).

5)    An evaluation and report of monitoring during subsequent years as determined by the ERC.

6)    An evaluation and report of monitoring results of recreation flow releases.  The schedule for this report shall be determined by the ERC.

·       Provide recommendations concerning flow releases and Project operation for inclusion in any reports to be submitted by Licensee to FERC.  The ERC may also identify non-Project factors which influence achieving the desired ecological outcomes.

·       The ERC may adopt goals and objectives for the biological parameters or resources being monitored and evaluated.

·       Modify schedules and procedures set forth in Appendix B for preparing data and reports as may be necessary to achieve the objectives provided herein.

 

 

Monitoring Data and Other Information:  The data collected under the monitoring programs will be compiled and distributed annually by January 15, or an alternate date agreeable to the ERC and FS, to each ERC member and FS by the ERC member responsible for performing the monitoring. Each ERC member shall be responsible for sharing in a timely manner information of which it is aware that is relevant to the work of the ERC.

 


Annual Report:  Licensee shall submit a draft annual report to the ERC and FS each year.  This report shall summarize the results of any ongoing ecological monitoring or study effort, changes that are to be implemented under the license and do not require FERC approval, proposed changes for which Licensee will request FERC or FS approval, including a proposed schedule for such approval, and a summary of any unresolved issues and proposed actions to resolve such issues.  All ERC members and FS shall have 30 days to review and comment on a draft of the annual report prior to its submittal to FERC.

 

Flow Cap Evaluations, Recommendations and Measures Implemented by ERC:

All flow cap evaluations, recommendations and measures implemented by the ERC will require that the ERC make an affirmative determination of the benefit of such action.  This determination shall be based on consideration of all power and non-power benefits, cost effectiveness, other impacts of the proposed measures, the use of the best scientific information available, and sound scientific methods.

 

Decision Making and Dispute Resolution:  The ERC members shall work collaboratively to make decisions and resolve issues assigned to the ERC under this Settlement.  Consistent with Paragraph 2.6 of this Settlement, FS shall be responsible for decisions within FS’ existing authority, including issuance of Section 4(e) Conditions and approvals thereunder.  FS acknowledges that the ERC shall be responsible for decisions that are assigned to ERC under this Settlement and that are not within the FS’ existing authority.  Further, FS and ERC acknowledge their mutual intent that, consistent with Paragraph 2.6 of this Settlement, the Section 4(e) Conditions shall provide for cooperation with regard to any decisions that are assigned to the ERC and that are also within the FS’ authority.

 

Reference documents to be used by the ERC shall include, but not be limited to, the new Project license, this Settlement, relevant FERC orders, and the Basin Plan

 

If the participating ERC members are unable to reach mutual agreement on an issue, the dispute resolution procedures provided in Paragraph 4.9.1 - Paragraph 4.9.3 of this Settlement shall be used.   In the event a disputed issue is not resolved in a timely manner, Licensee shall prepare and file a request that FERC, FS, or other agency with jurisdiction over the dispute, as appropriate, decide the issue in a timely manner.  Each ERC member and FS shall be free to provide its support for Licensee’s filing or to file separate comments.  

 

Notwithstanding the forgoing, in the event of a dispute over (a) whether to construct the Prattville Intake Modifications, or which modifications to construct, or (b) whether to implement additional temperature control measures in accordance with Paragraph 4 of Appendix A, Section I, the matter shall be resolved by the Chief of the SWRCB, Division of Water Rights, after use of alternative dispute resolution procedures as may be specified by the Division Chief.  The Division Chief’s determination shall be subject to administrative and judicial review in accordance with the statutes, regulations, and case law governing the SWRCB. The Division Chief’s determination shall be subject to the limitations of Paragraph 5 of Appendix A, Section I.

 

Funding:  Each member to the ERC shall be responsible for funding its representation on the ERC and, to the extent the internal resources of an agency allows, assisting in data collection and other efforts of the ERC at its own cost.  Study efforts that require the collection of data by Licensee or a consultant shall be paid for by Licensee.  Contracts for work funded by Licensee shall be entered into and directed by Licensee unless otherwise mutually agreed. 

 

Section III.  Habitat Mitigation

 

1.  Humbug Valley. - To provide additional enhancement to the fishery and wildlife resources within the North Fork Feather River watershed, Licensee will make specified phased improvements to its Humbug Valley land presently leased to a third party for cattle grazing.  Licensee land, encompassing approximately 2,300 acres, is located in the general vicinity of Township 27 North, Range 6 East; Township 26 North, Range 7 East, Township 26 North, Range 6 East; and Township 27 North, Range 7 East, Mount Diablo Base and Meridian.  A map is included in Attachment to this Agreement.

 

A.  PHASE A, as described in this section, shall commence following issuance of a New Project License for the Project and proceed on a mutually acceptable schedule.

 

a)    Licensee, in consultation with the ERC and FS, shall develop and implement a plan to design, construct, and maintain the following in an approximately 230 acre parcel (Attachment I, Parcel A) of land in the upper Humbug Valley as generally described in the August 6, 1989, report by Dr. Lee Erickson, entitled “Humbug Valley Irrigation System Assessment”:

 

i)     Approximately 1.5 miles of wire cattle fencing and appropriate cattle guards, or additional fencing, commencing the first summer season following issuance of a New Project License and as mutually agreed to accomplish the purposes of this Phase A.

ii)   Four (4) stream improvements, at locations to be mutually agreed upon by the ERC.  Scheduling to be mutually agreed upon by ERC.

iii) Selective planting of riparian vegetation.  Scheduling to be mutually agreed upon by the ERC.

iv)  Limited or prohibited, as necessary, cattle grazing for 3 to 5 years to be followed by controlled grazing at levels which will not adversely affect fisheries, riparian vegetation or water quality.  Scheduling to be mutually agreed upon by the ERC.

 

b)    For use as a planning tool, Licensee shall prepare, with the concurrence of ERC in consultation with FS, and implement within one year of issuance of the New Project License  a general resource management plan that addresses the following goals:

 

i)     Improve aquatic and riparian habitat of Yellow Creek.

ii)   Minimize consumptive water use under the present grazing lease.

iii) Minimize erosion and transport of sediment to downstream areas.

iv)  Evaluate the compatibility of grazing with future resource needs.

v)    Make recommendations for the best use of the existing resources.

 

c)    Within the riparian zone of Yellow Creek bounded by the existing split-rail cedar fence, commonly referred to as the “Cal-Trout fence”, Licensee shall identify species and develop and implement methods for vegetating the riparian zone and establishing “islands” of vegetated habitat along the stream, leaving open space between islands to enhance fly fishing opportunities.

 

d)    To minimize cattle intrusion into the riparian zone of Yellow Creek, Licensee shall construct fencing which closes the gap in the Cal-Trout fence at Yellow Creek campground.  If the fence encloses the campground, cattle guards shall be installed on the road through the campground.

 

e)    Licensee shall armor two existing cattle fords within the Cal-Trout fence.

 

B.  PHASE B, as described in this Section, shall commence in June, 2006, and be implemented within one year.

 

a)    Licensee, in consultation with the ERC and FS , shall develop and implement a plan to design, construct and maintain the following in an approximately 160 acre parcel of land (Attachment I, Parcel B), in the upper Humbug Valley as described in the August 6, 1989, report by Dr. Lee Erickson, entitled “Humbug Valley Irrigation System Assessment”:

 

i)     Approximately 0.5 miles of wire cattle fencing.

ii)   A minimum of four (4) stream improvements at locations to be mutually agreed upon by the ERC.

iii) Selective planting of riparian vegetation.

iv)  Limited cattle grazing for 3 to 5 years to be followed by controlled grazing at levels which will not adversely affect fisheries, riparian vegetation or water quality.

 

C)  PHASE C, as described in this Section, shall be implemented during the period from 2011 until license expiration, in addition to work performed under PHASE B.

 

a)    The ERC and FS shall review the needs for further enhancement work within Humbug Valley and shall meet at least once annually to determine collectively the extent of enhancement necessary.  Licensee shall provide the following funding for future enhancement work resulting from the Committee recommendations:

 

i)     For the years 2011 through 2020, Licensee shall provide annual funding of $25,000 (2000 dollars) starting in 2011 and escalated from 2000 to the year of payment as specified in Paragraph 4.5.5 of this Settlement.

ii)   For the years 2021 through the year of license expiration, Licensee shall provide annual funding of $12,000 (2000 dollars) escalated to the year of payment as specified in Paragraph 4.5.5 of this Settlement.

 

b)    To implement this Phase C, the parties may establish an interest-bearing account and appropriate procedures for the accounting and disbursement of funds.  Any funds remaining in the account upon termination of this Agreement shall be returned to Licensee.

 

2.  Future Changes and Access.  Nothing in the Agreement shall encumber or limit any legal or beneficial right Licensee may have in the Humbug Valley lands provided that Licensee agrees to allow continued public access to Humbug Valley Lands to the same extent that such access has occurred in the past.  This access has included vehicle access on existing roads and foot access on stream banks and lands.  If Licensee sells, leases, subdivides, or otherwise changes the legal nature of the lands from their present status, all successors in interest shall be required to perform Licensee’s obligations under this Agreement during the remaining term of the Agreement.

 

3.  Fishing Regulations.  For the preservation and improvement of fishery and recreation resources, the California Department of Fish and Game shall within one year following signature of this agreement, request the California Fish and Game Commission to designate the North Fork Feather River from Belden Bridge to Cresta Powerhouse (excluding reservoirs) as a catch-and -release-only (artificial lures, barbless hooks and zero bag limit) recreation fishery.  All Parties to this agreement shall support and actively work to seek the California Fish and Game Commission’s approval of the request.

 

4.  Outside Funding.  For the purposes of improving and enhancing public recreation, FS shall within two years following signature of this Settlement, request the California Department of Boating and Waterways for matching funding for river access facilities proposed pursuant to Section VI of Appendix A of this Settlement. All Parties to this Settlement shall support and actively work to seek the California Boating and Waterways approval of the request.

 

5.  Fishery Habitat Improvements.  Licensee shall make the following fishery and riparian habitat improvements in addition to the improvements included in Appendix A:

 

A)  Subject to approval by Caltrans, within one year of issuance of a New Project License, maintain the existing fish ladder located on Rush Creek, a tributary of the East Branch North Fork Feather River.

 

Section IV.  Block Loading

 

To minimize the frequency of 1) fluctuation in the river stage and 2) Ramping Rates that may be above the natural rise or fall rate of the NFFR, Licensee has implemented a practice of Block Loading Belden Powerhouse at times when the flow at the NF 57 stream gage is between the Minimum River Flow and 3,000 cfs.  Within this flow range, if the flow rate on Belden needs to be increased or decreased from Block Loading levels between 0 and 40 MW, Licensee shall, to the extent reasonably possible, make adjustments to Belden Powerhouse flows so as not to exceed, below Project dams, the basic Ramping Rates in Appendix A, Section II.5.A.  Licensee cannot operate Belden Powerhouse between 40 and 70 MW and if a transition between these levels is needed, Licensee will attempt to accomplish this transition with as little impact on these ramping rates as possible.  Licensee agrees to continue this Block Loading practice during March, April and May until such time as a level for Ramping Rates may be established under Licensee’s Project No. 2105 license such that such fluctuations are no longer a concern.

 

Bucks Creek Powerhouse feeds water into Cresta Reservoir and is typically cycled to follow daily system electric loads.  As the maximum flow rate of this powerhouse is less than 400 cfs and the impact of cycling is damped by Cresta Reservoir, Block Loading is not required through Bucks Creek Powerhouse.

 

Section V.  Monitoring Plan

 

Introduction

 

This outline describes the monitoring program proposed to meet the needs of this Settlement.  It has been limited to those items that are considered to be essential for determining if the identified resource management objectives are being met.  Funding for these monitoring efforts would be provided by Licensee.  Participation in the ERC and any monitoring by the resource agencies or other interested members of the ERC or FS will be at their own expense.

 

This Settlement provides for an “initial” set of Project Minimum River Flows to be implemented for a 5-year period, followed by two successive 5-year periods with modified Minimum River Flow regimes.  Monitoring would be required during these periods to enable the ERC and FS to determine if resource management objectives are achievable and being met.  Analysis of monitoring results from first two 5-year periods would be used by the ERC and FS along with other information to determine any desired changes in Minimum River Flow for the third 5-year period. 

 

The duration of the monitoring program would span 15 qualifying study years (as defined below).  Monitoring conducted during the three successive 5-year periods (i.e., years 1-5, years 6-10, and years 11-15) would represent resource conditions during each of these periods of modified streamflows.  Year 1 is defined as the first full year following issuance of a New Project License starting on January 1.  Monitoring of some elements conducted in year 1 would update baseline resource conditions at the beginning of the “initial” set of Project Minimum River Flows.

 

Overall Program

 

The ERC shall oversee completion of this monitoring program.  The monitoring plan specifies methods, timing, and rationale for monitoring.  However, prior to implementation, Licensee shall prepare final monitoring study plans, in consultation with the ERC and FS , and file the plans with FERC.  Licensee shall file with FERC, members of the ERC and FS, an annual report or reports summarizing the results of the monitoring effort as provided in Appendix B, Section II and the Water Temperature Monitoring Plan in Appendix A, Section I.

 

Qualifying Study Years 1-15 Within Monitoring Plan

 

During study years 1-15, Licensee shall implement the following monitoring plan in coordination with the ERC and FS.  The monitoring shall be conducted as described below, although exceptions to the monitoring plan can be made if the ERC determines that:  (1) there is a more appropriate or preferable methodology to use than that described in the monitoring plan, or (2) monitoring may be reduced because resource objectives have been met. 

 

It is the intent of this Settlement to implement three 5-year tests of various Minimum River Flows, Pulse Flows and Ramping Rates; however the duration of qualifying study years in the second or third 5-year period may be extended to compensate for the occurrence of critically dry years.  In years 1-5, flows shall be implemented as described in Table A of this Settlement and biological monitoring shall be conducted as described in this monitoring plan.  In the event that critically dry year flow releases interrupt the second or third 5-year test, the timing of that 5-year test sequence may be adjusted.  The following examples of adjustments to the test sequence were developed by the environmental subcommittee on February 23, 2000:

 

a)     Year 6, Year 7, Critically Dry Year, Grace Year, Year 8, Year 9, Year 10 (Seven years total in study sequence)

b)     Year 6, Year 7, Year 8, Year 9, Critically Dry Year, (Five years total, no “Year 10”)

c)     Year 6, Critically Dry Year, Critically Dry Year, Year 6 (Restart five year test sequence)

d)     Year 6, Year 7, Year 8, Critically Dry Year, Grace Year, Year 9, Year 10 (Seven years total in study sequence)

 

A “grace year” is defined as an additional year added to the planned test sequence during the second or third 5-year test periods primarily to allow for recovery of fish populations from possible effects of reduced flows during a critically dry year.  Monitoring is not proposed during a critically dry year in second or third test period, but would resume in the grace year in addition to the other qualifying years of the 5-year sequence.

 

Fish Populations

 

Method:  Electrofishing during late summer/fall at a maximum of 9 stations first monitored by CDFG 1989.  Snorkel surveys of index sections (such as those being conducted for the Poe Project) will be attempted if visibility permits.

 

Years:  1, 3, 4, 5, 8, 9, 10, 13, 14, 15

 

Rationale:  Year 1 sampling provides baseline data to represent populations at the start of the evaluation period.  Sampling in the last 3 years of each 5-year period provides multiple years for comparison to the objective, with sufficient response time to new streamflow regimes.

 

Creel Census

 

Method:  Angler surveys will be conducted using a comparable approach to CDFG 1989. 

 

Years:  1, 3, 4, 5, 8, 9, 10, 13, 14, 15

 

Rationale:  Selection of years is same as for the Fish Populations monitoring element. 

 

Tributary Trout Production 

 

Method:  Downstream migrant trapping to identify timing and relative production of juvenile trout will be conducted as feasible in three to five creeks, including Chambers, Bucks, and Grizzly creeks.  Sampling is proposed 2 consecutive days a week from June through September.  The intensity of the sampling may be adjusted based on the judgment of the ERC.

 

Years:  1, 3, 4, 5, 8, 9, 10, 13, 14, 15

 

Rationale:  Selection of years will provide an indication of trout recruitment from key tributaries concurrent with the fish population and creel surveys. 

 

Spawning Channel Evaluation 

 

Method:  Downstream migrant trapping to identify timing and relative production of juvenile trout will be conducted in spawning channels proposed for Milk Ranch and Opapee creeks.  Sampling is proposed 2 consecutive days a week from June through September.  In addition, observations of use by spawning trout (presence of spawning fish or redds) will also be attempted.

 

Years:  1, 2, 3, 4, 5, 8, 9, 10, 13, 14, 15

 

Rationale:  Evaluation in years 1 and 2 will provide an initial indication of spawning channel performance. If spawning channels are not completed in year 1, no supplemental years are proposed for the evaluation beyond those outlined above.  Monitoring in other years will provide both an evaluation of spawning channel performance and an indication of trout recruitment from spawning channels concurrent with the fish population and creel surveys. 

 

Macroinvertebrates

 

Method:  California Stream Bioassessment Procedure will be used during late summer/fall to survey benthic macroinvertebrates in the Rock Creek and Cresta reaches, NFFR between the Belden Reach and Belden PH, and the East Branch NFFR.  Study reaches sampled in 1999 will be targeted; additional sites may be included as determined feasible and necessary by the ERC and FS.  A reference site on the M.F. Feather River near Milsap Bar will also be added if determined feasible by the ERC and FS.  North Fork Feather River stations will be sampled at the same time in the Poe, Belden, and Seneca reaches as part of the monitoring program for Projects 2107 and 2105.  All results will be reported together to CDFG and other interested members of the ERC and FS in order to facilitate review on a watershed basis.  To create a stronger tool for assessment of stream integrity, the sampling methodology may be amended or modified by the ERC and FS.

 

Years:  1, 3, 4, 5, 8, 9, 10, 13, 14, 15

 

Rationale:   The years identified above are the same as for the Fish Populations monitoring element.  However, since invertebrates respond more quickly than fish to changes in flow, the ERC and FS will determine the actual study years based on water year type, with a sampling program that includes a minimum of three study years out of any given five-year test sequence.  Selection of sample sites in the Rock Creek and Cresta reaches was based on random selection of three riffles within population of identified suitable sites.  Other riffle types in the Rock Creek and Cresta reaches were judged to either be unsafe for sampling at higher minimum flow, and/or to have substrate (i.e. boulders) that will inappropriately limit the sensitivity of the CSBP analysis.  Sites in the NFFR above Belden PH and in the EBNFFR provide control reaches upstream of Rock Creek-Cresta to help evaluate the effect of floods and fine sediment produced in the watershed upstream of the Project.  An additional site in the MFFR near Milsap Bar will provide areference site with similar geomorphology to Rock Creek-Cresta.  Application of the CSBP to evaluate minimum instream flows is experimental and may be discontinued if the ERC and FS, concludes that the approach is not useful. 

 

Recreation and Pulse Flow Evaluation

 

Method:  A study design will be developed by the ERC and FS, sixty days prior to the initiation of scheduled recreation or Pulse Flow releases, to evaluate the effects of recreation and Pulse Flows (and associated Ramping Rates) on the aquatic ecology.  The study will be designed to evaluate the range of flows and Ramping Rates contained in the in-stream and recreation flow schedules.  In developing the study design, the ERC and FS will consider evaluating effects on (1) amphibian egg masses, (2) tadpoles, (3) fish, (4) macroinvertebates, (5) periphyton, (6) hyporheic community (7) birds, and (8) mammals.  This evaluation will consider both effects on habitat as well as populations, and will include as a major component, actual surveys conducted during, or immediately before and after actual flow events.  Draft study outlines prepared by the USFWS (1999) and AW (2000) and other relevant information will be considered by the ERC and FS.   The ERC and FS will determine the methodology, location, frequency, timing, and duration of data collection.  The ERC and FS will also determine the sequence of Ramping Rates and flow levels to be monitored, within the specified flow ranges described in the in-stream and recreation flow proposal.  The actual timing and frequency of flow events may also be adjusted by the ERC and FS, with accepted biological justification.  The study design developed by the ERC and FS will receive a scientific peer review prior to final acceptance.

 

Years:  1, 2, 3, 4, and 5 (or choice of five alternative years to better ensure surveys during appropriate conditions or water year types).  In the event of a positive change in the frequency of recreation flows, up to five additional years of monitoring, if the ERC and FS determine the need for supplemental  data.

 

Rationale:  These surveys are needed to evaluate the impact of manufactured flow pulses (including proposed Ramping Rates) on amphibians, fish, and invertebrates.  The flow schedule and Ramping Rates will be studied by the ERC and FS to determine if they have adverse, beneficial or neutral effect on the river restoration goals previously identified by this Settlement group.  This effort will define both beneficial and significant adverse effects, and the metrics to be used in this determination.  The volume and number of manufactured flow pulses may be modified if the ERC and FS find, through biologic monitoring, that these flows are having significant adverse biologic effects.

 

Riparian Vegetation

 

Method:  Riparian response to the flow regime in Table A would be monitored as a function of species richness (diversity of species present), plant vigor (growth and reproduction), and population demographics (age structure, mortality and recruitment of key indicator species).  These data would be collected along permanently established transects.  Baseline (pre-flow adjustment) data would be collected at each location in the year prior to start of riparian test flows.  Baseline data would include releve¢ sampling to determine the existing riparian community type (in the sense of Holland, 1992) at each sample location.  All sampling would be scheduled for the late summer of the final year of each five year flow period.

 

Years:  1, 5, 10, 15

 

Rationale.  Collection of transect data provides for a detailed evaluation of riparian vegetation response in the Rock Creek and Cresta reaches.  Year 1 sampling provides baseline data to represent the riparian plant community at the start of the evaluation period.  Monitoring at the end of each 5-year period provides an index of changes in riparian conditions over that period of modified streamflow (it should be noted that 5 years is a relatively short response time for riparian vegetation). 

 

Terrace Plantings

 

Monitoring to evaluate the effectiveness of terrace plantings shall track survival, vigor and canopy development of riparian species established at these sites and maintained through accepted horticultural techniques.  Specific performance goals (percent survival and canopy cover of vegetation) will be set for this restoration work.  Monitoring will be designed to measure these performance parameters, and to determine whether goals are being met.  Monitoring will be conducted once each year in the late spring after leaf-out.

 

Years:  1, 2, 3 (Year 1 in this case is the first year following planting)

 

Rationale.  Evaluation of the success of terrace plantings for an initial three-year period will assure establishment of vegetation and permit timely replacement of individual plants as needed to meet performance goals.  If Licensee determines that replacement of individual plants is unlikely to correct the problems identified, the ERC and FS will meet to decide on the appropriate course of action. 

 


River Sediment Management (Drum and Radial Gate Operation to Promote Bedload Movement through Reservoirs)

 

Method:  If this program is feasible (dependent on safety of program for dam operation), the test program will be conducted for a period of 5 years.  In order to monitor the effectiveness of the drum and radial gates operational test program, seven river cross sections shall be selected and monitored using Wolman Pebble Counts, sieve analysis, and embeddedness measurements.  In addition, reservoir bathymetry measurements shall be made in Rock Creek and Cresta reservoirs as determined by the ERC and FS.  During the five-year test program, monitoring shall be conducted during the summer of each year that reservoirs are operated to promote bedload movement.

 

Year:  1, 2, 3, 4, 5 (Data collected in Year 1 is expected to be a baseline year prior to implementing a river sediment management program.  The timing and duration of the monitoring may be adjusted by the ERC and FS, in consideration of water year type and Project operations.

 

Rationale:  Monitoring of Wolman Pebble Counts, sieve analysis, and embeddedness measurements at permanent cross-sections provides the basis for evaluating changes in riffle sediment composition.  In particular, this monitoring is to test whether the sediment management program is effective in increasing the amount of gravel present in riffles and bars in the Rock Creek and Cresta reaches.  Year 1 sampling provides baseline data prior to any modification of reservoir operating procedures.  Monitoring after the high spring runoff period during a 5-year test period provides an index of changes in channel sediment composition during the sediment management test.  Reservoir sampling during the test period will help to verify the effect of such a sediment program on safe dam operation.

 

Gravel Placement Experiment (If the river sediment management experiment is determined to be unsuccessful)

 

Method:  If the ERC and FS determine that the experimental river sediment management program is not effective in increasing the amount of gravel present in riffle habitat (or is not safe to implement), USFWS has requested that an experimental program of gravel addition be evaluated.  The following program is proposed:

1.     Experimental gravel placement would be using a maximum of 200 cubic yards of clean washed river gravel purchased from a commercial aggregate supplier. 

2.     Gravel would be placed at sites in the Rock Creek and Cresta reaches to be selected by the ERC and FS; these sites would have to be truck-accessible without significant road preparation or development.

3.     Gravel would be placed near the margin of the river, within the zone inundated at summer minimum flow.

4.     Gravel placement is proposed in late February or early March, prior to rainbow trout spawning.

5.     The success of gravel placement will be determined by its retention at the placement site or its immediate vicinity.  For example, gravel placed in the run below the Rodgers Flat bridge could be evaluated by the amount of gravel retained in the first riffle downstream.  Initial criteria for evaluating gravel retention at or near a placement site is proposed as  20% remaining after the end of the spring runoff period of the year in which it was placed.  Observations of trout spawning (such presence of spawning fish or redds) will also be attempted.

 

Years:  Beginning year 6, duration may extend for up to 5 years, depending on the rate of gravel placement and the water year type (e.g. in a wet year the flow may be too high to permit timely placement).  Program may begin sooner than year 6 if the ERC and FS determine that the river sediment management test is ineffective or unsafe.

 

Rationale:  The high sediment transport capacity of the NFFR makes it unlikely that mechanical placement of gravel could be effectively tracked other than locally at or near the deposition site.  In order to be considered effective, a significant fraction of the gravel must be able to remain in place through at least the proposed seven mandatory Pulse Flow releases.

 

Water Temperature Monitoring:

 

See Appendix A, Section I for water temperature monitoring requirements.

 


Appendix C

 

Richard Locke

Law Department

Pacific Gas and Electric Company

77 Beale Street, Mail Code B30A

San Francisco, CA 94142

Ph. 415-973-6616  FAX 415-973-5520

rfl6@pge.com

 

Randy Livingston

Pacific Gas and Electric Company

Manager, Hydro Generation

245 Market Street., N11C

San Francisco, CA  94142

Ph. 415-973-5323,  FAX 415-973-3967

rsl3@pge.com

 

Craig Bolger

Pacific Gas and Electric Company

DeSabla Hydro Superintendent

15449 Humbug Road

Magalia, CA  95954

Ph. 530-896-4471, 

chb2@pge.com

 

Mark Madrid

Forest Supervisor

USDA Forest Service

Plumas National Forest

159 Lawrence Street

Quincy, CA  95971

Ph. 530-283-2050  FAX  530-283-4156

 

Jack Gipsman

Office of General Counsel, USDA

33 New Montgomery, 17th Floor

San Francisco, CA  94105

Ph. 415-744-3166, FAX  415-744-3170

jack.gipsman@usda.gov

 


Banky Curtis

Manager, Region 2

California Department of Fish and Game

1701 Nimbus Road, Suite A

Rancho Cordova, CA  95670

Ph. 916-358-2899,  FAX 916-358-2912

bcurtis@dfg.ca.gov

 

Nancee M. Murray

Legal Office

California Department of Fish and Game

1416 9th St., 12th Floor

Sacramento, CA  95814

Ph. 916-654-3818  FAX 916-654-3805

nmurray@dfg.ca.gov

 

Wayne S. White

Field Supervisor

United States Department of the Interior

Fish and Wildlife Service

2800 Cottage Way, Room W-2605

Sacramento, CA  95825

Ph.916-414-6610  FAX

 

Jim Canaday

State Water Resources Control Board

901 P Street

Sacramento, CA  95814

Ph. 916-657-2208, Fax 916-657-1485

jcanaday@waterrights.swrcb.ca.gov

 

Mr. Rob Shulman 

Plumas County Counsel

520 West Main St., Room 302

Quincy, CA 95971

Ph. 530-283-6240  FAX

robshulman@countyofplumas.com

 


Richard Roos-Collins

Natural Heritage Institute

2140 Shattuck Avenue, Suite 500

Berkeley, CA  94704-1222

Ph. 510-644-2900, FAX 510-644-4428

rrcollins@n-h-i.org

 

John Gangemi

Conservation Director, American Whitewater

482 Electric Avenue

Bigfork, MT  59911

Ph. 406-837-3155, FAX 406-837-3156

jgangemi@digisys.net

 

Jen Carville

Policy Advocate

Friends of the River

915 20th Street

Sacramento, CA  95814

Ph. 916-442-3155, FAX 916-442-3396

jen@friendsoftheriver.org

 

Mr. Nate Rangel 

CA Outdoors 

PO Box 401 

Coloma, CA  95613-0401

Ph. 530-626-7385 x203  FAX 530-626-9268

nate@raftcalifornia.com

 

Jim Edmondson

California Trout

5436 Westview Court Road

Westlake Village, CA  91362

Ph. 818-865-2888  FAX 818-707-2459

Troutmd@earthlink.net

 

Curtis Knight

California Trout

P. O. Box 650

Mt. Shasta, CA  96067

Ph. 530-926-3755  FAX 530-926-8909

CAKnight@JPS.net


Kevin Lewis

Shasta Paddlers

4641 Hornbeck Ln

Anderson, CA  96007-2631

Ph. 530-2118722  FAX 530-221-5981

klewis@snowcrest.net

 

Dave Steindorf

Chico Paddleheads

179 Valley Ridge Dr.

Paradise, CA  95964

Ph. 530-876-0430,  FAX 530-876-1335

dsteind@telis.org